[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
culvert |
9.000 - 9.006
|
6.000 |
30.0665381000, 78.8347484000 |
Estimation Done |
0 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Cause way |
18.020 - 18.030
|
10.000 |
30.0573527800, 78.8542250000 |
Estimation Done |
8 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
0.325
|
-- |
30.0533333300, 78.8305555600 |
Estimation Done |
7 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
0.375
|
-- |
30.0534611100, 78.8311500000 |
Estimation Done |
6 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
0.625
|
-- |
30.0538194400, 78.8334500000 |
Estimation Done |
6 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
0.860
|
-- |
30.0539333300, 78.8336083300 |
Sanctioned |
6 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
1.425
|
-- |
30.0547555600, 78.8347527800 |
Estimation Done |
6 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
1.725
|
-- |
30.0562194400, 78.8537611100 |
Estimation Done |
7 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
2.100
|
-- |
30.0558583300, 78.8428222200 |
Estimation Done |
6 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
2.525
|
-- |
30.0565666700, 78.8403083300 |
Sanctioned |
6 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
2.650
|
-- |
30.0574361100, 78.8391694400 |
Estimation Done |
5 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
3.025
|
-- |
30.0566472200, 78.8360277800 |
Estimation Done |
6 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
3.200
|
-- |
30.0558583300, 78.8343750000 |
Estimation Done |
5 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
3.375
|
-- |
30.0559972200, 78.8336666700 |
Estimation Done |
0 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
3.450
|
-- |
30.0555083300, 78.8324333300 |
Estimation Done |
6 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
3.550
|
-- |
30.0560666700, 78.8318000000 |
Estimation Done |
5 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
3.625
|
-- |
30.0561166700, 78.8311555600 |
Estimation Done |
5 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
3.850
|
-- |
30.0565194400, 78.8291333300 |
Estimation Done |
5 |
|
|
|
ok |
Aug 2024 |
[3121]
Pokhrikhet Chorkandi Majkholi Naila Bhawai Masho motor road
|
Scupper |
4.025
|
-- |
30.0570527800, 78.8274472200 |
Estimation Done |
6 |
|
|
|
ok |
Aug 2024 |
[3127]
Kimgadi link road
|
culvert |
0.816
|
-- |
29.9614250000, 78.9094750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3127]
Kimgadi link road
|
culvert |
0.990
|
-- |
29.9624720000, 78.9106580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3127]
Kimgadi link road
|
Scupper |
0.135
|
-- |
29.9569583000, 78.9082083000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3127]
Kimgadi link road
|
Scupper |
0.336
|
-- |
29.9583720000, 78.9091194000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3127]
Kimgadi link road
|
Scupper |
0.579
|
-- |
29.9602805000, 78.9100944000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3127]
Kimgadi link road
|
Scupper |
0.856
|
-- |
29.9616666000, 78.9097220000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3127]
Kimgadi link road
|
Scupper |
0.990
|
-- |
29.9624720000, 78.9106580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
culvert |
6.700 - 6.707
|
7.000 |
30.0885050000, 78.8513100000 |
Estimation Done |
6 |
2021-06-01 00:00:00 |
|
0 |
|
Aug 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
0.150
|
-- |
30.0876160000, 78.8350970000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
0.325
|
-- |
30.0881830000, 78.8364300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
0.475
|
-- |
30.0884300000, 78.8380830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
0.625
|
-- |
30.0884333300, 78.8380830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
0.725
|
-- |
30.0885700000, 78.8403500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
0.825
|
-- |
30.0887080000, 78.8413970000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
1.075
|
-- |
30.0885800000, 78.8413830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
1.650
|
-- |
30.0877027000, 78.8374027000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
1.725
|
-- |
30.0876083300, 78.8376110000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
1.775
|
-- |
30.0877770000, 78.8389550000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
1.950
|
-- |
30.0878138000, 78.8406750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
2.100
|
-- |
30.0879410000, 78.8414410000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
2.225
|
-- |
30.0877300000, 78.8429000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
2.350
|
-- |
30.0882194000, 78.8441380000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
2.825
|
-- |
30.0878250000, 78.8439416000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
2.900
|
-- |
30.0874610000, 78.8434750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
3.175
|
-- |
30.0868360000, 78.8415940000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
3.530
|
-- |
30.0868400000, 78.8439100000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
3.575
|
-- |
30.0872050000, 78.8441750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
3.700
|
-- |
30.0872580000, 78.8455660000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
3.775
|
-- |
30.0872805500, 78.8462888000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
3.875
|
-- |
30.0872805000, 78.8471611000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
4.325
|
-- |
30.0883410000, 78.8494200000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
4.450
|
-- |
30.0880361000, 78.8482940000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
4.525
|
-- |
30.0877194000, 78.8479910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
4.625
|
-- |
30.0867900000, 78.8480700000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
4.725
|
-- |
30.0860770000, 78.8480160000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
4.850
|
-- |
30.0866110000, 78.8470500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
4.925
|
-- |
30.0864750000, 78.8469055000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
5.025
|
-- |
30.0859270000, 78.8475300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
5.100
|
-- |
30.0857910000, 78.8482300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
5.175
|
-- |
30.0858500000, 78.8489610000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
5.425
|
-- |
30.0876880000, 78.8495830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
5.950
|
-- |
30.0889360000, 78.8517470000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
6.325
|
-- |
30.0887880000, 78.8519910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
6.375
|
-- |
30.0891470000, 78.8528800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
6.700
|
-- |
30.0879800000, 78.8525520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
6.875
|
-- |
30.0868500000, 78.8521270000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
6.950
|
-- |
30.0863800000, 78.8514250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3134]
Beda Bagad motor road
|
Scupper |
7.150
|
-- |
30.0860000000, 78.8517500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
culvert |
5.975
|
-- |
30.9470083000, 78.8956138000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Cautionary board |
0.000
|
-- |
30.9466220000, 78.8899500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
0.200
|
-- |
29.9622972000, 78.8885472000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
0.300
|
-- |
29.9618750000, 78.8888833000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
0.390
|
-- |
29.9613440000, 78.8894300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
0.885
|
-- |
29.9589694000, 78.8894305000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
0.990
|
-- |
29.9587610000, 78.8886830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
1.040
|
-- |
29.9585750000, 78.8881910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
1.250
|
-- |
29.9572610000, 78.8890100000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
1.700
|
-- |
29.9555000000, 78.8861805000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
1.755
|
-- |
29.9551416000, 78.8864250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
1.850
|
-- |
29.9548100000, 78.8865561000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
1.900
|
-- |
29.9546220000, 78.8877160000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
2.000
|
-- |
29.9540270000, 78.8891500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
2.160
|
-- |
29.9539190000, 78.8902800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
2.225
|
-- |
29.9534190000, 78.8905520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
2.450
|
-- |
29.9534194000, 78.8908160000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
2.600
|
-- |
29.9539970000, 78.8908100000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
2.750
|
-- |
29.9541805000, 78.8910190000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
2.800
|
-- |
29.9534800000, 78.8912200000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
3.180
|
-- |
29.9507630000, 78.8886100000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
3.350
|
-- |
29.9499080000, 78.8873300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
3.450
|
-- |
29.9495500000, 78.8879300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
3.550
|
-- |
29.9495500000, 78.8888100000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
3.900
|
-- |
29.9482130000, 78.8906500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
4.000
|
-- |
30.9481400000, 78.8922400000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
4.250
|
-- |
30.9469020000, 78.8930800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
4.350
|
-- |
30.9462527000, 78.8935580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
4.450
|
-- |
30.9453611000, 78.8935630000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
4.550
|
-- |
30.9451110000, 78.8936300000 |
Treatment in Progress |
8 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
4.650
|
-- |
30.9460638000, 78.8943080000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
4.750
|
-- |
30.9466910000, 78.8942000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
4.850
|
-- |
30.9467630000, 78.8945690000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
4.925
|
-- |
30.9455270000, 78.8942770000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
5.000
|
-- |
30.9448610000, 78.8940910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
5.300
|
-- |
30.9431583000, 78.8934300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
5.400
|
-- |
30.9431940000, 78.8935800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
5.700
|
-- |
30.9452910000, 78.8946100000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Scupper |
5.950
|
-- |
30.9462940000, 78.8952830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Parapet |
0.000 - 0.053
|
52.500 |
30.9632000000, 78.8899500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Parapet |
1.000 - 1.018
|
18.000 |
30.9586750000, 78.8882583000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3135]
Bharatpur Sundari Nauly Dabra motor road
|
Parapet |
2.000 - 2.014
|
13.500 |
30.9539610000, 78.8899900000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
culvert |
2.000
|
-- |
29.8489880000, 78.8884972200 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Cause way |
0.190 - 0.196
|
6.000 |
29.8462833000, 78.9001250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
0.010
|
-- |
29.8462638000, 78.9015580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
0.260
|
-- |
29.8464805000, 78.8993027000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
0.355
|
-- |
29.8465250000, 78.8984916000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
0.470
|
-- |
29.8470694000, 78.8975190000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
0.580
|
-- |
29.8464583300, 78.8970416000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
0.800
|
-- |
29.8460944000, 78.8956027000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
0.870
|
-- |
29.8462190000, 78.8950800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
0.930
|
-- |
29.8463000000, 78.8943800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
0.955
|
-- |
29.8463444000, 78.8924910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
1.000
|
-- |
29.8461520000, 78.8922750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
1.330
|
-- |
29.8471440000, 78.8914300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
1.450
|
-- |
29.8476722000, 78.8910580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
1.650
|
-- |
29.8483880000, 78.8897111000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3139]
Kolakhal Jajedi motor road
|
Scupper |
2.000
|
-- |
29.8489888000, 78.8884970000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
culvert |
8.475
|
-- |
29.8980500000, 78.9378300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
culvert |
11.325
|
-- |
29.8898870000, 78.9451900000 |
Estimation Done |
8 |
|
|
|
Protection work Required for Right side Abutment of down stream |
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Cause way |
4.650 - 4.662
|
12.000 |
29.8977472000, 78.9288388000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Informatory board |
0.000
|
-- |
29.9057583000, 78.9207400000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
0.025
|
-- |
29.9054200000, 78.9205100000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
0.125
|
-- |
29.9050361000, 78.9200550000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
0.250
|
-- |
29.9041000000, 78.9197940000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
0.350
|
-- |
29.9038520000, 78.9187940000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
0.450
|
-- |
29.9032700000, 78.9179270000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
0.700
|
-- |
29.9019083000, 78.9166138000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
1.200
|
-- |
29.9023600000, 78.9182630000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
1.500
|
-- |
29.9033100000, 78.9209500000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
1.575
|
-- |
29.9035972000, 78.9213610000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
1.600
|
-- |
29.9037500000, 78.9215610000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
1.700
|
-- |
29.9041805000, 78.9224305000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
1.850
|
-- |
29.9044410000, 78.9230500000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
2.050
|
-- |
29.9042500000, 78.9253910000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
3.100
|
-- |
29.9019080000, 78.9258860000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
3.275
|
-- |
29.9029160000, 78.9271638000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
3.325
|
-- |
29.9029583000, 78.9276472000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
3.450
|
-- |
29.9033660000, 78.9285000000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
3.950
|
-- |
29.9040833000, 78.9314330000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
4.075
|
-- |
29.9034194000, 78.9288416000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
4.250
|
-- |
29.9021020000, 78.9308000000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
4.275
|
-- |
29.9019160000, 78.9306100000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
4.425
|
-- |
29.9012250000, 78.9300000000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
4.675
|
-- |
29.8998720000, 78.9289830000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
4.850
|
-- |
29.8987250000, 78.9280800000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
5.050
|
-- |
29.8976600000, 78.9121270000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
5.425
|
-- |
29.8954138000, 78.9261380000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
5.525
|
-- |
29.8953750000, 78.9269000000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
5.725
|
-- |
29.8965660000, 78.9273250000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
5.775
|
-- |
29.8965472000, 78.9251400000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
5.900
|
-- |
29.8962100000, 78.9264583000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
5.975
|
-- |
29.8956800000, 78.9262500000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
6.125
|
-- |
29.8948600000, 78.9258083000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
6.525
|
-- |
29.8931972000, 78.9236400000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
6.625
|
-- |
29.8926610000, 78.9233400000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
6.700
|
-- |
29.8926638000, 78.9239800000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
6.750
|
-- |
29.8928000000, 78.9245638000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
7.050
|
-- |
29.8934472000, 78.9261200000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
7.250
|
-- |
29.8940940000, 78.9286638000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
7.300
|
-- |
29.8943720000, 78.9291630000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
7.350
|
-- |
29.8945830000, 78.9292750000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
7.900
|
-- |
29.8957694000, 78.9335830000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
8.275
|
-- |
29.8972940000, 78.9361500000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
8.375
|
-- |
29.8980138000, 78.9367916000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
8.575
|
-- |
29.8975400000, 78.9377360000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
8.675
|
-- |
29.8966660000, 78.9375083000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
8.700
|
-- |
29.8963940000, 78.9375305000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
8.775
|
-- |
29.8960972000, 78.9367138000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
8.925
|
-- |
29.8952300000, 78.9365160000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
9.375
|
-- |
29.8936300000, 78.9360000000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
9.475
|
-- |
29.8931000000, 78.9358580000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
9.750
|
-- |
29.8919940000, 78.9360910000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
9.925
|
-- |
29.8910020000, 78.9375690000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
9.975
|
-- |
29.8907300000, 78.9379160000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
10.225
|
-- |
29.8910300000, 78.9402100000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
10.500
|
-- |
29.8909800000, 78.9417700000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
10.525
|
-- |
29.8910138000, 78.9421660000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
10.725
|
-- |
29.8912500000, 78.9436940000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
10.775
|
-- |
29.8915580000, 78.9440700000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
11.050
|
-- |
29.8905910000, 78.9445700000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
11.400
|
-- |
29.8892250000, 78.9451027000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
11.450
|
-- |
29.8889470000, 78.9445100000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Scupper |
11.550
|
-- |
29.8889020000, 78.9436380000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
4.675 - 4.679
|
4.000 |
29.8998720000, 78.9289830000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
4.850 - 4.852
|
2.000 |
29.8987250000, 78.9280800000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
5.050 - 5.052
|
2.000 |
29.8976660000, 78.9121200000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
5.425 - 5.429
|
4.000 |
29.8954100000, 78.9269000000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
5.725 - 5.729
|
4.000 |
29.8965600000, 78.9273250000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
5.775 - 5.779
|
4.000 |
29.8965400000, 78.9251440000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
6.525 - 6.531
|
6.000 |
29.8931000000, 78.9236400000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
6.700 - 6.706
|
6.000 |
29.8926638000, 78.9239880000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
6.775 - 6.781
|
6.000 |
29.8926600000, 78.9233400000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
7.050 - 7.053
|
3.000 |
29.8934472000, 78.9272300000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
7.250 - 7.256
|
6.000 |
29.8940944000, 78.9286630000 |
Treatment in Progress |
6 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
7.300 - 7.306
|
6.000 |
29.8943720000, 78.9291630000 |
Treatment in Progress |
6 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
7.350 - 7.356
|
6.000 |
29.8945800000, 78.9292750000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
8.475 - 8.502
|
27.000 |
29.8980440000, 78.9376600000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
11.300 - 11.345
|
45.000 |
29.8897380000, 78.9449000000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3140]
Chalkudiya Masmoli Saknoli Devkundai motor road
|
Parapet |
11.400 - 11.404
|
4.000 |
29.8892250000, 78.9451020000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
culvert |
5.200
|
-- |
29.8802194000, 78.8022944000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
0.165
|
-- |
29.8703305000, 78.7949630000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
0.595
|
-- |
29.8705944000, 78.7952200000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
0.756
|
-- |
29.8708055500, 78.7952083300 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
1.160
|
-- |
29.8722660000, 78.7918361000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
1.300
|
-- |
29.8734500000, 78.7921830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
1.640
|
-- |
29.8755000000, 78.7946888000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
1.720
|
-- |
29.8757360000, 78.7954440000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
1.820
|
-- |
29.8762583000, 78.7962833000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
1.960
|
-- |
29.8774333000, 78.7964944000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
2.080
|
-- |
29.8784444000, 78.7966055000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
2.190
|
-- |
29.8792944000, 78.7972110000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
2.270
|
-- |
29.8798805000, 78.7973300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
2.360
|
-- |
29.8806880000, 78.7974550000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
2.500
|
-- |
29.8816472000, 78.7982220000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
3.000
|
-- |
29.8847720000, 78.8005130000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
3.120
|
-- |
29.8857194000, 78.8006138000 |
Treatment in Progress |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
3.200
|
-- |
29.8863300000, 78.8001722000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
3.420
|
-- |
29.8881555500, 78.7996166000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
3.720
|
-- |
29.8901000000, 78.7999861100 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
4.050
|
-- |
29.8883720000, 78.8006500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
4.150
|
-- |
29.8877277000, 78.8012694000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
4.900
|
-- |
29.8825222000, 78.8038500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
5.130
|
-- |
29.8805972000, 78.8034520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
5.350
|
-- |
29.8795520000, 78.8020722000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
5.500
|
-- |
29.8790083000, 78.8010610000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
5.730
|
-- |
29.8770750000, 78.8006440000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
5.800
|
-- |
29.8762880000, 78.8008694000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
5.960
|
-- |
29.8771110000, 78.8018027000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
6.630
|
-- |
29.8757700000, 78.8050600000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
6.900
|
-- |
29.8755000000, 78.8076305000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
7.000
|
-- |
29.8757888000, 78.8093611000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
7.280
|
-- |
29.8752690000, 78.8108800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
7.480
|
-- |
29.8749250000, 78.8128550000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
7.730
|
-- |
29.8746750000, 78.8142666000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
7.950
|
-- |
29.8753130000, 78.8129110000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
8.180
|
-- |
29.8759555000, 78.8117520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
8.580
|
-- |
29.8752111000, 78.8151444000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
9.100
|
-- |
29.8772472000, 78.8180666000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
9.310
|
-- |
29.8762444000, 78.8162083300 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
9.380
|
-- |
29.8763520000, 78.8155410000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
9.565
|
-- |
29.8767130000, 78.8150000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
9.635
|
-- |
29.8768220000, 78.8156630000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
9.805
|
-- |
29.8776500000, 78.8169360000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
10.505
|
-- |
29.8783550000, 78.8152050000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
11.300
|
-- |
29.8813444000, 78.8128110000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
11.800
|
-- |
29.8840305000, 78.8124520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
12.000
|
-- |
29.8834916000, 78.8137110000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
12.200
|
-- |
29.8828805500, 78.8148611100 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
12.600
|
-- |
29.8815000000, 78.8173750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
12.650
|
-- |
29.8811500000, 78.8174250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
12.700
|
-- |
29.8807416000, 78.8181800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
12.800
|
-- |
29.8811444000, 78.8195130000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
13.700
|
-- |
29.8819050000, 78.8257611000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
13.900
|
-- |
29.8821000000, 78.8244610000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
13.950
|
-- |
29.8820861000, 78.8240777000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
14.000
|
-- |
29.8822910000, 78.8229861100 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
14.700
|
-- |
29.8839720000, 78.8181750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
14.800
|
-- |
29.8852694000, 78.8180472000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
15.000
|
-- |
29.8868361000, 78.8172972000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
15.200
|
-- |
29.8880250000, 78.8165111000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
15.300
|
-- |
29.8881083000, 78.8163805000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
15.700
|
-- |
29.8900160000, 78.8146110000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
15.800
|
-- |
29.8907300000, 78.8151360000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
15.850
|
-- |
29.8912888000, 78.8157470000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
16.000
|
-- |
29.8919410000, 78.8166940000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
16.900
|
-- |
29.8993270000, 78.8165520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Scupper |
17.100
|
-- |
29.9010770000, 78.8176944000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3141]
Kot Malla to Kot Talla Kandiya Kulasu Reethakhal motor road
|
Parapet |
19.000 - 19.009
|
9.000 |
29.9024083000, 78.8176800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
culvert |
2.600
|
-- |
29.9142380000, 78.8671500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
culvert |
4.700
|
-- |
29.9214583000, 78.8624380000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
0.100
|
-- |
29.9111555000, 78.8683138000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
0.160
|
-- |
29.9104583000, 78.8671833000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
0.300
|
-- |
29.9099055000, 78.8659440000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
0.530
|
-- |
29.9096222000, 78.8660833000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
0.610
|
-- |
29.9093805000, 78.8659660000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
0.720
|
-- |
29.9090000000, 78.8654860000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
0.800
|
-- |
29.9089500000, 78.8647220000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
0.900
|
-- |
29.9086770000, 78.8637020000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
1.000
|
-- |
29.9091690000, 78.8639630000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
1.400
|
-- |
29.9110138000, 78.8632305000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
1.620
|
-- |
29.9110027000, 78.8629000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
1.680
|
-- |
29.9114083000, 78.8626361000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
1.880
|
-- |
29.9126194000, 78.8612861100 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
2.330
|
-- |
29.9133520000, 78.8646690000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
2.500
|
-- |
29.9138100000, 78.8661630000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
2.700
|
-- |
29.9147361000, 78.8665080000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
2.900
|
-- |
29.9164555500, 78.8659055500 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
3.000
|
-- |
29.9173194000, 78.8660330000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
3.530
|
-- |
29.9176160000, 78.8641166000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
3.670
|
-- |
29.9170527000, 78.8653050000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
3.920
|
-- |
29.9170194000, 78.8647000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
4.150
|
-- |
29.9176972000, 78.8624527000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
4.450
|
-- |
29.9203722000, 78.8619300000 |
Estimation Done |
3 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
4.800
|
-- |
29.9217944000, 78.8615000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
4.920
|
-- |
29.9212972000, 78.8610000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
5.240
|
-- |
29.9201660000, 78.8602440000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
5.320
|
-- |
29.9195080000, 78.8600550000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
5.430
|
-- |
29.9186111000, 78.8594440000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
5.480
|
-- |
29.9183444000, 78.8593277000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
5.610
|
-- |
29.9174472000, 78.8585694000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
5.980
|
-- |
29.9159220000, 78.8564833000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
6.070
|
-- |
29.9160638000, 78.8556972000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
6.210
|
-- |
29.9169970000, 78.8549972000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
6.520
|
-- |
29.9148722000, 78.8539330000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3142]
Kundeel khalyudaanda khedgaon Thapla Maanjhi Malkot motor road
|
Scupper |
6.620
|
-- |
29.9144300000, 78.8531200000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
culvert |
3.700
|
-- |
29.9697750000, 78.8946880000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Cautionary board |
0.345
|
-- |
29.9577080000, 78.8803500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Cautionary board |
1.700
|
-- |
29.9640750000, 78.8849200000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Cautionary board |
2.050
|
-- |
29.9650500000, 78.8872700000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Cautionary board |
3.970
|
-- |
29.9681610000, 78.8946277000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Cautionary board |
4.190
|
-- |
29.9674800000, 78.8948580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Cautionary board |
4.320
|
-- |
29.9667222000, 78.8946472200 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Cautionary board |
5.550
|
-- |
29.9610270000, 78.8979880000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
0.100
|
-- |
29.9567055000, 78.8785888000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
0.175
|
-- |
29.9570333300, 78.8791888000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
0.310
|
-- |
29.9578916600, 78.8800361100 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
0.450
|
-- |
29.9580277000, 78.8812970000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
0.595
|
-- |
29.9589055000, 78.8813660000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
0.638
|
-- |
29.9592916000, 78.8815166000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
0.840
|
-- |
29.9602277000, 78.8823916000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
1.050
|
-- |
29.9602555000, 78.8845055000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
1.280
|
-- |
29.9612972000, 78.8843416000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
1.330
|
-- |
29.9616416000, 78.8841000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
1.430
|
-- |
29.9624500000, 78.8837190000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
1.560
|
-- |
29.9633805000, 78.8837472200 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
1.630
|
-- |
29.9638660000, 78.8842083300 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
1.810
|
-- |
29.9646190000, 78.8855861100 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
1.900
|
-- |
29.9650944000, 78.8862388000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
2.130
|
-- |
29.9657194000, 78.8874750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
2.230
|
-- |
29.9664472000, 78.8875277000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
2.300
|
-- |
29.9663000000, 78.8883270000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
2.600
|
-- |
29.9670910000, 78.8900000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
2.700
|
-- |
29.9667361000, 78.8909194000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
2.990
|
-- |
29.9669611000, 78.8918861100 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
3.200
|
-- |
29.9685861000, 78.8925444000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
3.400
|
-- |
29.9698050000, 78.8922083000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
3.450
|
-- |
29.9697250000, 78.8931220000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
3.600
|
-- |
29.9699527700, 78.8940083300 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
3.760
|
-- |
29.9693361100, 78.8950472000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
3.880
|
-- |
29.9687000000, 78.8953330000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
3.900
|
-- |
29.9683555000, 78.8948550000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
3.950
|
-- |
29.9681610000, 78.8946270000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
3.990
|
-- |
29.9676916000, 78.8954861000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
4.190
|
-- |
29.9674888000, 78.8948580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
4.440
|
-- |
29.9660027000, 78.8948690000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
4.520
|
-- |
29.9654638000, 78.8951250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
4.630
|
-- |
29.9647160000, 78.8947610000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
4.900
|
-- |
29.9636388000, 78.8950050000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
4.950
|
-- |
29.9635166000, 78.8960880000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
4.990
|
-- |
29.9635388000, 78.8973250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
5.200
|
-- |
29.9633027000, 78.8974805000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
5.300
|
-- |
29.9621388000, 78.8975666000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
5.400
|
-- |
29.9612944000, 78.8970610000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
5.500
|
-- |
29.9611000000, 78.8976694400 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
5.600
|
-- |
29.9613666600, 78.8983944000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
5.700
|
-- |
29.9620083000, 78.8992111000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
5.900
|
-- |
29.9630972000, 78.8998000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
5.950
|
-- |
29.9632000000, 78.9002027000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
5.990
|
-- |
29.9630777000, 78.9008194000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
6.200
|
-- |
29.9633861000, 78.9015110000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
6.500
|
-- |
29.9643916000, 78.9021830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
6.740
|
-- |
29.9657630000, 78.9020110000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
6.770
|
-- |
29.9660580000, 78.9018300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
6.830
|
-- |
29.9663583000, 78.9021777000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Scupper |
6.990
|
-- |
29.9666750000, 78.9035600000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Parapet |
0.090 - 0.110
|
20.000 |
29.9601160000, 78.8847750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Parapet |
0.383 - 0.493
|
110.000 |
29.9577330000, 78.8807500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Parapet |
1.280 - 1.290
|
10.000 |
29.9612970000, 78.8843416000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Parapet |
1.815 - 1.981
|
166.000 |
29.9647700000, 78.8857500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Parapet |
1.930 - 1.954
|
24.000 |
29.9667770000, 78.8898861000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Parapet |
2.780 - 2.882
|
102.000 |
29.9663722000, 78.8912910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Parapet |
3.250 - 3.270
|
20.000 |
29.9687940000, 78.8927600000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Parapet |
3.975 - 3.995
|
20.000 |
29.9680300000, 78.8948160000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Parapet |
4.900 - 4.950
|
50.000 |
29.9636380000, 78.8950055000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Parapet |
5.390 - 5.406
|
16.000 |
29.9615805000, 78.8969880000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Parapet |
6.390 - 6.398
|
8.000 |
29.9637611000, 78.9024166000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Puccadrain |
0.000 - 0.150
|
150.000 |
29.9560100000, 78.8783270000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Puccadrain |
1.410 - 1.465
|
55.000 |
29.9623190000, 78.8838300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Puccadrain |
2.200 - 2.220
|
20.000 |
29.9662722000, 78.8875416000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Puccadrain |
3.540 - 3.617
|
77.000 |
29.9696660000, 78.8936910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Puccadrain |
3.730 - 3.765
|
35.000 |
29.9693360000, 78.8950470000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Puccadrain |
6.280 - 6.297
|
17.000 |
29.9633861000, 78.9015111000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3159]
Choubattakhal Dantha motor road
|
Puccadrain |
6.730 - 6.751
|
21.000 |
29.9657638000, 78.9020111000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Cause way |
8.825 - 8.831
|
6.000 |
30.0786182200, 78.8390676000 |
Estimation Done |
7 |
|
|
|
condition is ok |
Aug 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
0.135
|
-- |
30.1185470000, 78.8174520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
0.700
|
-- |
30.1143080000, 78.8197000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
1.070
|
-- |
30.1111160000, 78.8198440000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
1.620
|
-- |
30.1107916000, 78.8242972000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
1.800
|
-- |
30.1093300000, 78.8249830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
2.150
|
-- |
30.1073166000, 78.8255610000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
2.550
|
-- |
30.1055777000, 78.8275610000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
2.600
|
-- |
30.1049416000, 78.8278270000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
2.875
|
-- |
30.1030520000, 78.8266250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
3.100
|
-- |
30.1008520000, 78.8260888000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
3.280
|
-- |
30.0995050000, 78.8256360000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
3.920
|
-- |
30.0946470000, 78.8262300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
4.050
|
-- |
30.0943805000, 78.8253250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
4.175
|
-- |
30.0945833000, 78.8247270000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
4.275
|
-- |
30.0939555000, 78.8239611000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
4.400
|
-- |
30.0926444000, 78.8235527000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
4.550
|
-- |
30.0923583300, 78.8225250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
4.600
|
-- |
30.0919000000, 78.8232916000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
4.725
|
-- |
30.0911833000, 78.8235194400 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
4.775
|
-- |
30.0909277700, 78.8242305000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
4.875
|
-- |
30.0905861000, 78.8251916000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
5.100
|
-- |
30.0903222000, 78.8249722200 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
5.150
|
-- |
30.0905222200, 78.8283550000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
5.200
|
-- |
30.0906166600, 78.8286277000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
5.275
|
-- |
30.0907027000, 78.8291333000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
5.350
|
-- |
30.0907166000, 78.8296750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
5.400
|
-- |
30.0906222200, 78.8301611100 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
5.450
|
-- |
30.0909472000, 78.8306111000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
5.575
|
-- |
30.0915583000, 78.8313055000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
5.875
|
-- |
30.0904861100, 78.8322861100 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
6.025
|
-- |
30.0912500000, 78.8334111000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
6.100
|
-- |
30.0909611000, 78.8340800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
6.175
|
-- |
30.0902805000, 78.8345138000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
6.225
|
-- |
30.0897888000, 78.8351138000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
6.375
|
-- |
30.0900361000, 78.8358444000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
6.925
|
-- |
30.0882580000, 78.8359361000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
7.025
|
-- |
30.0877250000, 78.8348916000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
7.100
|
-- |
30.0870055000, 78.8345083000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
7.200
|
-- |
30.0867527000, 78.8332250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
7.250
|
-- |
30.0864500000, 78.8332250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
7.450
|
-- |
30.0855472000, 78.8329050000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
7.525
|
-- |
30.0851222000, 78.8329055000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
7.700
|
-- |
30.0833750000, 78.8333777000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Scupper |
7.900
|
-- |
30.0820720000, 78.8350520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Slide Zone |
11.000 - 11.030
|
30.000 |
30.0776700000, 78.8357100000 |
Identified |
7 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Slide Zone |
26.000 - 26.030
|
30.000 |
30.0334270000, 78.8159361000 |
Identified |
7 |
|
|
|
|
Jan 2024 |
[434]
Sungarkhal Sikukhal Jwalpadevi motor road
|
Slide Zone |
30.000 - 30.030
|
30.000 |
30.0093027000, 78.8116160000 |
Identified |
8 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Cause way |
5.620 - 5.638
|
18.000 |
30.0000055000, 78.9402660000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Cause way |
5.710 - 5.715
|
5.000 |
29.9996900000, 78.9404750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Crash barrier |
1.640 - 1.684
|
44.000 |
30.0031050000, 78.9347300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Informatory board |
0.000
|
-- |
30.0021361000, 78.9266500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Informatory board |
0.500
|
-- |
30.0023083000, 78.9269630000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Informatory board |
6.000
|
-- |
29.9978861000, 78.9393100000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Informatory board |
6.920
|
-- |
29.9918470000, 78.9359500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
0.100
|
-- |
30.0027750000, 78.9270700000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
0.210
|
-- |
30.0033410000, 78.9278472000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
0.320
|
-- |
30.0035940000, 78.9288583000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
0.400
|
-- |
30.0041130000, 78.9294000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
0.460
|
-- |
30.0044050000, 78.9299550000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
0.550
|
-- |
30.0043611000, 78.9308750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
0.600
|
-- |
30.0040900000, 78.9311000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
1.010
|
-- |
30.0037083300, 78.9324861100 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
1.100
|
-- |
30.0041200000, 78.9340520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
1.210
|
-- |
30.0033410000, 78.9355630000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
1.520
|
-- |
30.0031500000, 78.9355305000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
1.700
|
-- |
30.0037305000, 78.9340416000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
1.860
|
-- |
30.0031500000, 78.9327110000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
2.000
|
-- |
30.0029805000, 78.9299083000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
2.010
|
-- |
30.0021380000, 78.9327080000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
2.100
|
-- |
30.0023050000, 78.9320270000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
2.150
|
-- |
30.0028020000, 78.9315330000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
2.270
|
-- |
30.0037050000, 78.9307305000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
2.340
|
-- |
30.0035470000, 78.9300830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
2.410
|
-- |
30.0029805000, 78.9299083000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
2.560
|
-- |
30.0017300000, 78.9296270000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
2.720
|
-- |
30.0006080000, 78.9290800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
3.010
|
-- |
29.9989611000, 78.9287833000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
3.110
|
-- |
29.9974690000, 78.9283470000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
3.300
|
-- |
29.9966527000, 78.9284050000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
3.650
|
-- |
29.9989080000, 78.9294900000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
3.810
|
-- |
29.9999220000, 78.9300630000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
4.010
|
-- |
30.0009940000, 78.9308900000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
4.100
|
-- |
30.0001380000, 78.9313520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
4.410
|
-- |
29.9987400000, 78.9323910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
4.610
|
-- |
30.0000750000, 78.9340830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
4.810
|
-- |
29.9993583000, 78.9346694000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
4.830
|
-- |
29.9980944000, 78.9346583000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
5.240
|
-- |
29.9986910000, 78.9367610000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
5.450
|
-- |
29.9996305000, 78.9385138000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
6.020
|
-- |
29.9972000000, 78.9388500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
6.080
|
-- |
29.9968020000, 78.9386000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
6.205
|
-- |
29.9963880000, 78.9381910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
6.410
|
-- |
29.9949611000, 78.9379416000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
6.470
|
-- |
29.9943361000, 78.9380000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
6.630
|
-- |
29.9931972000, 78.9375583000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Scupper |
6.750
|
-- |
29.9925410000, 78.9369100000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
0.100 - 0.106
|
6.000 |
30.0027750000, 78.9270700000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
0.550 - 0.556
|
6.000 |
30.0043610000, 78.9308750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
1.210 - 1.213
|
3.000 |
30.0033410000, 78.9355000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
1.300 - 1.306
|
6.000 |
30.0020000000, 78.9359700000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
1.520 - 1.526
|
6.000 |
30.0031500000, 78.9355300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
2.010 - 2.016
|
6.000 |
30.0021380000, 78.9327000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
2.270 - 2.273
|
3.000 |
30.0037050000, 78.9307300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
2.410 - 2.413
|
3.000 |
30.0029800000, 78.9299083000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
2.560 - 2.563
|
3.000 |
30.0017300000, 78.9296270000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
3.010 - 3.016
|
6.000 |
29.9989610000, 78.9287830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
3.110 - 3.116
|
6.000 |
29.9974690000, 78.9283347000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
3.650 - 3.653
|
3.000 |
29.9989080000, 78.9294900000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
3.810 - 3.813
|
3.000 |
29.9999220000, 78.9300630000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
4.010 - 4.013
|
3.000 |
30.0009940000, 78.9308900000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
4.100 - 4.103
|
3.000 |
30.0001380000, 79.9313520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
4.410 - 4.413
|
3.000 |
29.9987400000, 78.9323910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
4.830 - 4.833
|
3.000 |
29.9980940000, 78.9346580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
5.240 - 5.243
|
3.000 |
29.9986910000, 78.9367610000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3125]
Damdeval Gadari Jhalpadi motor road
|
Parapet |
6.100 - 6.136
|
36.000 |
29.9996630000, 78.9405770000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3131]
Tugdhunda link road
|
Cause way |
3.000 - 3.006
|
6.000 |
30.0998500000, 78.8328920000 |
Estimation Done |
5 |
|
|
0 |
ok |
Jul 2024 |
[3131]
Tugdhunda link road
|
Cause way |
3.200 - 3.207
|
7.000 |
30.1449493000, 78.7766531000 |
Estimation Done |
5 |
2015-06-29 00:00:00 |
2015-06-30 00:00:00 |
0 |
ok |
Jul 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
0.066
|
-- |
29.9541777700, 78.8762944000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
0.170
|
-- |
29.9540361100, 78.8753694000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
0.362
|
-- |
29.9537220000, 78.8742833000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
0.440
|
-- |
29.9538888000, 78.8735638000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
0.491
|
-- |
29.9535611000, 78.8732250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
0.538
|
-- |
29.9536250000, 78.8727520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
0.600
|
-- |
29.9533055000, 78.8722190000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
0.689
|
-- |
29.9530194000, 78.8720110000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
0.723
|
-- |
29.9523472000, 78.8720410000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
0.736
|
-- |
29.9526000000, 78.8720027000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
0.780
|
-- |
29.9529722200, 78.8715722200 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
1.200
|
-- |
29.9543250000, 78.8718222000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
1.280
|
-- |
29.9547444000, 78.8725750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
1.730
|
-- |
29.9541305500, 78.8704000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
1.900
|
-- |
29.9527833000, 78.8706333000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Cautionary board |
1.930
|
-- |
29.9524250000, 78.8701580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
0.037
|
-- |
29.9540160000, 78.8765722000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
0.138
|
-- |
29.9540750000, 78.8756805000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
0.223
|
-- |
29.9537388000, 78.8750600000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
0.274
|
-- |
29.9534527000, 78.8747190000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
0.318
|
-- |
29.9532638000, 78.8742690000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
0.572
|
-- |
29.9534083000, 78.8725361000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
0.600
|
-- |
29.9533055000, 78.8722194400 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
0.714
|
-- |
29.9525527000, 78.8724500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
0.730
|
-- |
29.9526000000, 78.8720027000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
1.140
|
-- |
29.9544305000, 78.8712472000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
1.200
|
-- |
29.9543250000, 78.8718220000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
1.260
|
-- |
29.9546160000, 78.8721972000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
1.370
|
-- |
29.9547250000, 78.8720972000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
1.400
|
-- |
29.9545444000, 78.8718880000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
1.450
|
-- |
29.9546638000, 78.8713166000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
1.600
|
-- |
29.9547361000, 78.8704000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
1.740
|
-- |
29.9537444400, 78.8703638000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
1.840
|
-- |
29.9530166000, 78.8708020000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
1.910
|
-- |
29.9525000000, 78.8705166000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
2.140
|
-- |
29.9512444000, 78.8682277000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
2.230
|
-- |
29.9507111000, 78.8675833000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
2.430
|
-- |
29.9492833000, 78.8675638000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
2.650
|
-- |
29.9482222000, 78.8668610000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
2.750
|
-- |
29.9474500000, 78.8674000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
2.850
|
-- |
29.9469027000, 78.8672027000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
2.900
|
-- |
29.9464100000, 78.8674200000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
3.030
|
-- |
29.9459110000, 78.8662550000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
3.070
|
-- |
29.9458500000, 78.8659000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
3.160
|
-- |
29.9458970000, 78.8650166000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
3.400
|
-- |
29.9450690000, 78.8653300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
3.570
|
-- |
29.9445333000, 78.8669830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
3.670
|
-- |
29.9442916000, 78.8676250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
3.690
|
-- |
29.9441770000, 78.8678500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
3.800
|
-- |
29.9435250000, 78.8681690000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
3.870
|
-- |
29.9428300000, 78.8678470000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
4.190
|
-- |
29.9399900000, 78.8658190000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3153]
Latibo Dalibo Nai motor road
|
Scupper |
4.490
|
-- |
29.9378388000, 78.8627250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[8193]
Road from Arkani khandukhal Mucchiyali road to Tapradi via Sc basti Kulkhanyu
|
Cautionary board |
0.500
|
-- |
30.1986500000, 78.6821230000 |
Estimation Done |
9 |
2023-11-13 00:00:00 |
|
0 |
ok |
Aug 2024 |
[8193]
Road from Arkani khandukhal Mucchiyali road to Tapradi via Sc basti Kulkhanyu
|
Scupper |
0.250
|
-- |
30.1986140000, 78.6796300000 |
Estimation Done |
9 |
2021-09-15 00:00:00 |
|
0 |
ok |
Aug 2024 |
[8193]
Road from Arkani khandukhal Mucchiyali road to Tapradi via Sc basti Kulkhanyu
|
Scupper |
0.450
|
-- |
30.1982530000, 78.6813630000 |
Estimation Done |
8 |
2021-09-23 00:00:00 |
|
|
ok |
Aug 2024 |
[8193]
Road from Arkani khandukhal Mucchiyali road to Tapradi via Sc basti Kulkhanyu
|
Scupper |
0.600
|
-- |
30.1975140000, 78.6813700000 |
Estimation Done |
8 |
2021-09-01 00:00:00 |
|
0 |
ok |
Aug 2024 |
[8193]
Road from Arkani khandukhal Mucchiyali road to Tapradi via Sc basti Kulkhanyu
|
Scupper |
0.950
|
-- |
30.1968000000, 78.6791300000 |
Estimation Done |
8 |
2021-10-09 00:00:00 |
|
0 |
ok |
Aug 2024 |
[8193]
Road from Arkani khandukhal Mucchiyali road to Tapradi via Sc basti Kulkhanyu
|
Parapet |
0.250 - 0.252
|
2.000 |
30.1986140000, 78.6796300000 |
Estimation Done |
9 |
2023-11-09 00:00:00 |
|
0 |
ok |
Aug 2024 |
[8193]
Road from Arkani khandukhal Mucchiyali road to Tapradi via Sc basti Kulkhanyu
|
Parapet |
0.250 - 0.252
|
2.000 |
30.1986140000, 78.6796300000 |
Estimation Done |
9 |
2023-11-09 00:00:00 |
|
|
ok |
Aug 2024 |
[8193]
Road from Arkani khandukhal Mucchiyali road to Tapradi via Sc basti Kulkhanyu
|
Parapet |
0.450 - 0.452
|
2.000 |
30.1982530000, 78.6813630000 |
Estimation Done |
9 |
2023-11-05 00:00:00 |
|
0 |
ok |
Aug 2024 |
[8193]
Road from Arkani khandukhal Mucchiyali road to Tapradi via Sc basti Kulkhanyu
|
Parapet |
0.450 - 0.452
|
2.000 |
30.1982530000, 78.6813630000 |
Estimation Done |
9 |
2023-11-05 00:00:00 |
|
|
ok |
Aug 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Crash barrier |
0.025 - 0.055
|
30.000 |
30.2106410000, 78.7120520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Informatory board |
0.000
|
-- |
30.2105400000, 78.7120583000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
0.090
|
-- |
30.2109166000, 78.7125888000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
0.220
|
-- |
30.2115194400, 78.7133722000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
0.390
|
-- |
30.2125972000, 78.7130360000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
0.575
|
-- |
30.2138111000, 78.7132472000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
0.680
|
-- |
30.2146138000, 78.7136080000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
0.845
|
-- |
30.2156750000, 78.7128833000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
1.160
|
-- |
30.2159194000, 78.7130500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
1.300
|
-- |
30.2151050000, 78.7141000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
1.450
|
-- |
30.2139270000, 78.7140220000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
1.800
|
-- |
30.2152800000, 78.7145660000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
1.960
|
-- |
30.2163330000, 78.7141611000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
2.150
|
-- |
30.2164944000, 78.7142305000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Scupper |
2.260
|
-- |
30.2165555000, 78.7143720000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Parapet |
0.390 - 0.392
|
2.000 |
30.2125970000, 78.7130360000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Parapet |
0.575 - 0.577
|
2.000 |
30.2138110000, 78.7132470000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Parapet |
0.680 - 0.682
|
2.000 |
30.2146138000, 78.7136080000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Parapet |
0.845 - 0.847
|
2.000 |
30.2156750000, 78.7128830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Parapet |
1.160 - 1.162
|
2.000 |
30.2159194000, 78.7130500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Parapet |
1.300 - 1.302
|
2.000 |
30.2151050000, 78.7141000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Parapet |
1.450 - 1.452
|
2.000 |
30.2139270000, 78.7140220000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Parapet |
1.800 - 1.802
|
2.000 |
30.2152800000, 78.7145660000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Parapet |
1.960 - 1.962
|
2.000 |
30.2164940000, 78.7141611000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Parapet |
2.150 - 2.152
|
2.000 |
30.2164944000, 78.7142305000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Parapet |
2.260 - 2.262
|
2.000 |
30.2165555500, 78.7143720000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3154]
Dehalchori Manjeen Kanda motor road
|
Parapet |
2.400 - 2.450
|
50.000 |
30.2166300000, 78.7146300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3157]
Link road of Pokhra to Vishvidhyalaya
|
Crash barrier |
0.085 - 0.267
|
182.000 |
29.9089190000, 78.9070160000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3157]
Link road of Pokhra to Vishvidhyalaya
|
Scupper |
0.200
|
-- |
29.9089660000, 78.9067600000 |
Estimation Done |
2 |
|
|
|
|
Jan 2024 |
[3157]
Link road of Pokhra to Vishvidhyalaya
|
Scupper |
0.325
|
-- |
29.9080830000, 78.9067910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3157]
Link road of Pokhra to Vishvidhyalaya
|
Scupper |
0.400
|
-- |
29.9074000000, 78.9065300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3157]
Link road of Pokhra to Vishvidhyalaya
|
Scupper |
0.450
|
-- |
29.9069690000, 78.9065500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3157]
Link road of Pokhra to Vishvidhyalaya
|
Parapet |
0.035 - 0.085
|
50.000 |
29.9094160000, 78.9071080000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3157]
Link road of Pokhra to Vishvidhyalaya
|
Puccadrain |
0.020 - 0.447
|
427.000 |
29.9095000000, 78.9072800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Informatory board |
3.000
|
-- |
30.9552020000, 78.9369250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Informatory board |
5.780
|
-- |
29.9568130000, 78.9497080000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
0.280
|
-- |
29.9587800000, 78.9162160000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
0.600
|
-- |
29.9563860000, 78.9149690000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
0.700
|
-- |
29.9557972000, 78.9143410000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
0.780
|
-- |
29.9553410000, 78.9137000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
0.850
|
-- |
29.9548500000, 78.9132360000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
0.995
|
-- |
29.9537700000, 78.9117900000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
1.450
|
-- |
29.9531800000, 78.9131200000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
1.750
|
-- |
29.9537270000, 78.9159630000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
1.850
|
-- |
29.9539388000, 78.9165910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
1.900
|
-- |
29.9542027000, 78.9171050000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
1.950
|
-- |
29.9544440000, 78.9174880000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
1.990
|
-- |
29.9544880000, 78.9183520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
2.200
|
-- |
29.9547300000, 78.9198000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
2.350
|
-- |
29.9546970000, 78.9211250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
2.450
|
-- |
29.9546360000, 78.9219500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
2.550
|
-- |
29.9543520000, 78.9228630000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
2.650
|
-- |
29.9544500000, 78.9237580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
2.800
|
-- |
29.9546250000, 78.9251720000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
2.850
|
-- |
29.9549250000, 78.9274750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
2.900
|
-- |
29.9547083000, 78.9259972000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
2.950
|
-- |
29.9548470000, 78.9268250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
3.100
|
-- |
29.9549720000, 78.9279220000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
3.190
|
-- |
29.9549083000, 78.9291020000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
3.320
|
-- |
29.9548830000, 78.9302190000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
3.400
|
-- |
29.9551410000, 78.9309200000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
3.550
|
-- |
29.9552361000, 78.9326800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
3.800
|
-- |
29.9556250000, 78.9350380000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
3.900
|
-- |
29.9554190000, 78.9361080000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
3.950
|
-- |
29.9552300000, 78.9375000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
4.300
|
-- |
29.9550360000, 78.9398972000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
4.600
|
-- |
29.9539410000, 78.9413800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
4.700
|
-- |
29.9544160000, 78.9422690000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
4.840
|
-- |
29.9550940000, 78.9431361000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
5.150
|
-- |
29.9547050000, 78.9462520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
5.380
|
-- |
29.9546805000, 78.9475020000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
5.600
|
-- |
29.9557220000, 78.9489361000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
5.750
|
-- |
29.9568830000, 78.9497380000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
5.800
|
-- |
29.9575700000, 78.9514400000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
5.880
|
-- |
29.9577380000, 78.9513200000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
5.980
|
-- |
29.9574660000, 78.9505250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
6.195
|
-- |
29.9573380000, 78.9500138000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
6.350
|
-- |
29.9573380000, 78.9488720000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
6.400
|
-- |
29.9558360000, 78.9482970000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Scupper |
6.595
|
-- |
29.9568410000, 78.9477130000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
0.130 - 0.148
|
18.000 |
29.9596333000, 78.9171250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
0.281 - 0.332
|
51.000 |
29.9587800000, 78.9162166000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
0.473 - 0.488
|
15.000 |
29.9573690000, 78.9153000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
0.600 - 0.633
|
33.000 |
29.9563500000, 78.9148940000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
0.650 - 0.683
|
33.000 |
29.9561722000, 78.9146400000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
0.700 - 0.751
|
51.000 |
29.9557611000, 78.9143194000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
0.800 - 0.824
|
24.000 |
29.9552416000, 78.9135690000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
1.000 - 1.015
|
15.000 |
29.9537910000, 78.9117800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
1.130 - 1.172
|
42.000 |
29.9535250000, 78.9112160000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
1.240 - 1.246
|
6.000 |
29.9525610000, 78.9114520000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
1.330 - 1.372
|
42.000 |
29.9524220000, 78.9122600000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
1.550 - 1.577
|
27.000 |
29.9531580000, 78.9140580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
1.700 - 1.721
|
21.000 |
29.9534330000, 78.9153860000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
1.880 - 1.898
|
18.000 |
29.9540500000, 78.9169027000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
1.965 - 1.989
|
24.000 |
29.9544861000, 78.9179690000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
1.990 - 1.999
|
9.000 |
29.9544160000, 78.9184400000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
2.200 - 2.218
|
18.000 |
29.9545470000, 78.9203970000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
2.350 - 2.362
|
12.000 |
29.9546200000, 78.9213000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
2.600 - 2.612
|
12.000 |
29.9543083000, 78.9234666000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
2.700 - 2.718
|
18.000 |
29.9544270000, 78.9246110000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
2.800 - 2.821
|
21.000 |
29.9545660000, 78.9254610000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
3.200 - 3.212
|
12.000 |
29.9548160000, 78.9292250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
3.550 - 3.592
|
42.000 |
29.9551770000, 78.9327600000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
3.700 - 3.724
|
24.000 |
29.9552611000, 78.9342805000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
3.800 - 3.824
|
24.000 |
29.9556277000, 78.9350583000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
3.870 - 3.900
|
30.000 |
29.9554472200, 78.9352500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
3.960 - 3.984
|
24.000 |
29.9552630000, 78.9366190000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
3.970 - 3.991
|
21.000 |
29.9551694000, 78.9370020000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
3.990 - 4.032
|
42.000 |
29.9552333000, 78.9374888000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
4.150 - 4.183
|
33.000 |
29.9551160000, 78.9379472000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
4.300 - 4.330
|
30.000 |
29.9547833000, 78.9392600000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
4.400 - 4.436
|
36.000 |
29.9544200000, 78.9402500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
4.600 - 4.687
|
87.000 |
29.9539527000, 78.9413861000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
4.900 - 4.951
|
51.000 |
29.9546830000, 78.9440300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
4.970 - 4.988
|
18.000 |
29.9544910000, 78.9450000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
5.100 - 5.118
|
18.000 |
29.9546720000, 78.9458000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
5.150 - 5.162
|
12.000 |
29.9546940000, 78.9462270000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
5.300 - 5.327
|
27.000 |
29.9545330000, 78.9470000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3118]
Gawani Jhalpadi Damdeval motor road
|
Parapet |
5.380 - 5.401
|
21.000 |
29.9546610000, 78.9474910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
0.144
|
-- |
30.0769361000, 78.8417880000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
0.425
|
-- |
30.0768830000, 78.8392900000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
0.575
|
-- |
30.0761100000, 78.8382400000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
1.175
|
-- |
30.0751700000, 78.8350000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
1.275
|
-- |
30.0748720000, 78.8359500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
1.340
|
-- |
30.0742830000, 78.8358200000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
1.575
|
-- |
30.0734830000, 78.8363940000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
1.700
|
-- |
30.0728500000, 78.8361270000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
1.775
|
-- |
30.0725550000, 78.8359720000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
2.100
|
-- |
30.0732277000, 78.8370583000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
2.200
|
-- |
30.0724250000, 78.8370720000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
2.475
|
-- |
30.0719000000, 78.8357100000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
3.000
|
-- |
30.0714750000, 78.8357100000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
3.175
|
-- |
30.0720700000, 78.8346910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
3.360
|
-- |
30.0732250000, 78.8341000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3120]
Seekukhal Timli motor road
|
Scupper |
3.550
|
-- |
30.0737050000, 78.8325305000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
0.255
|
-- |
29.9603250000, 78.8543500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
0.314
|
-- |
29.9603050000, 78.8544580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
0.525
|
-- |
29.9613944000, 78.8558805000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
0.595
|
-- |
29.9609800000, 78.8563470000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
0.835
|
-- |
29.9609330000, 78.8559860000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
0.920
|
-- |
29.9605630000, 78.8554000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
0.990
|
-- |
29.9605194000, 78.8555800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
1.050
|
-- |
29.9606830000, 78.8559690000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
1.140
|
-- |
29.9599200000, 78.8560400000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
1.300
|
-- |
29.9588250000, 78.8562700000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
1.520
|
-- |
29.9571940000, 78.8559400000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
1.600
|
-- |
29.9567520000, 78.8557600000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
1.740
|
-- |
29.9557500000, 78.8554300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
1.870
|
-- |
29.9548970000, 78.8550500000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
1.900
|
-- |
29.9545190000, 78.8550300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
2.000
|
-- |
29.9538200000, 78.8551700000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
2.400
|
-- |
29.9532527000, 78.8568055000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
2.670
|
-- |
29.9525220000, 78.8565027000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
2.920
|
-- |
29.9504666000, 78.8563610000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
3.000
|
-- |
29.9497138000, 78.8563440000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
3.140
|
-- |
29.9488777000, 78.8561700000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
3.260
|
-- |
29.9494888000, 78.8556100000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
3.580
|
-- |
29.9479050000, 78.8532000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
3.750
|
-- |
29.9468800000, 78.8531220000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
3.800
|
-- |
29.9466220000, 78.8526080000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
4.070
|
-- |
29.9462000000, 78.8525020000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
4.150
|
-- |
29.9456020000, 78.8528333000 |
Sanctioned |
6 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
4.230
|
-- |
29.9449440000, 78.8529580000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
4.310
|
-- |
29.9444750000, 78.8526020000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
4.490
|
-- |
29.9449194000, 78.8512380000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
4.850
|
-- |
29.9423750000, 78.8496250000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
4.950
|
-- |
29.9419610000, 78.8489050000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
5.570
|
-- |
29.9379750000, 78.8479194000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
5.670
|
-- |
29.9373333000, 78.8484550000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
5.900
|
-- |
29.9375300000, 78.8493330000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
5.940
|
-- |
29.9378638000, 78.8494638000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3123]
Jandadevi Odgauv Bondarkhal motor road
|
Scupper |
6.180
|
-- |
29.9377940000, 78.8496361000 |
Sanctioned |
6 |
|
|
|
|
Jan 2024 |
[3133]
Road from km 1 of Sungarkhal Seekukhal Jawapa devi to gram Nisni, Naugoun Tandu
|
Scupper |
0.226
|
-- |
30.1110881000, 78.8194860000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3133]
Road from km 1 of Sungarkhal Seekukhal Jawapa devi to gram Nisni, Naugoun Tandu
|
Scupper |
0.570
|
-- |
30.1108860000, 78.8192910000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3133]
Road from km 1 of Sungarkhal Seekukhal Jawapa devi to gram Nisni, Naugoun Tandu
|
Scupper |
0.632
|
-- |
30.1113910000, 78.8193270000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3133]
Road from km 1 of Sungarkhal Seekukhal Jawapa devi to gram Nisni, Naugoun Tandu
|
Scupper |
0.868
|
-- |
30.1122916000, 78.8194200000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3133]
Road from km 1 of Sungarkhal Seekukhal Jawapa devi to gram Nisni, Naugoun Tandu
|
Scupper |
1.000
|
-- |
30.1108861000, 78.8188750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3133]
Road from km 1 of Sungarkhal Seekukhal Jawapa devi to gram Nisni, Naugoun Tandu
|
Scupper |
1.320
|
-- |
30.1097000000, 78.8191020000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3133]
Road from km 1 of Sungarkhal Seekukhal Jawapa devi to gram Nisni, Naugoun Tandu
|
Scupper |
1.620
|
-- |
30.1095805000, 78.8188970000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3136]
Nai bend to Dhasmani motor road
|
Scupper |
0.060
|
-- |
29.9336472000, 78.8548416000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3136]
Nai bend to Dhasmani motor road
|
Scupper |
0.238
|
-- |
29.9327800000, 78.8553800000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3136]
Nai bend to Dhasmani motor road
|
Scupper |
0.440
|
-- |
29.9315250000, 78.8561830000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3136]
Nai bend to Dhasmani motor road
|
Scupper |
0.560
|
-- |
29.9308750000, 78.8562300000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3136]
Nai bend to Dhasmani motor road
|
Scupper |
0.670
|
-- |
29.9303330000, 78.8568600000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3136]
Nai bend to Dhasmani motor road
|
Scupper |
0.950
|
-- |
29.9294720000, 78.8578750000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
16.000
|
-- |
29.8450270000, 78.9023850000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
16.050
|
-- |
29.8452270000, 78.9023860000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
16.200
|
-- |
29.8454270000, 78.9024850000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
16.400
|
-- |
29.8458280000, 78.9027840000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
17.000
|
-- |
29.8422070000, 78.9015630000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
17.100
|
-- |
29.8420070000, 78.9020300000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
17.200
|
-- |
29.8419080000, 78.9014630000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
17.600
|
-- |
29.8522080000, 78.9018630000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
18.000
|
-- |
29.8407500000, 78.9024980000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
18.100
|
-- |
29.8405000000, 78.9022980000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
18.200
|
-- |
29.8407500000, 78.9024980000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
18.400
|
-- |
29.8401820000, 78.9029430000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
18.600
|
-- |
29.8401900000, 78.9030430000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
19.000
|
-- |
29.8379350000, 78.9040770000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
19.200
|
-- |
29.8378350000, 78.9041780000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
19.400
|
-- |
29.8382350000, 78.9040900000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
19.800
|
-- |
29.8381830000, 78.9042780000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
20.100
|
-- |
29.8327630000, 78.9018520000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
20.200
|
-- |
29.8326630000, 78.9017730000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
20.400
|
-- |
29.8278660000, 78.8985780000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
20.600
|
-- |
29.8277650000, 78.8974780000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
20.800
|
-- |
29.8284360000, 78.8985780000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
21.200
|
-- |
29.8082160000, 78.9010000000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
21.400
|
-- |
29.8280180000, 78.9014000000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
21.800
|
-- |
29.8480200000, 78.9016000000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
22.100
|
-- |
29.8179150000, 78.9012000000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
22.200
|
-- |
29.8180180000, 78.9014100000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3144]
Bijorpani Kunjkhal Kolakhal Pandiyana Basdang Jaykot motor road
|
Scupper |
22.250
|
-- |
29.8181160000, 78.9013500000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3146]
Panchwati Devrajkhal motor road
|
Scupper |
0.105
|
-- |
29.9399166000, 78.8765861000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3146]
Panchwati Devrajkhal motor road
|
Scupper |
0.236
|
-- |
29.9389138000, 78.8766361000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3146]
Panchwati Devrajkhal motor road
|
Scupper |
0.801
|
-- |
29.9354833000, 78.8741194400 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3146]
Panchwati Devrajkhal motor road
|
Scupper |
0.992
|
-- |
29.9340833000, 78.8737722000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3146]
Panchwati Devrajkhal motor road
|
Scupper |
1.090
|
-- |
29.9334690000, 78.8732130000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3146]
Panchwati Devrajkhal motor road
|
Scupper |
1.180
|
-- |
29.9327916000, 78.8733888000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3146]
Panchwati Devrajkhal motor road
|
Scupper |
1.270
|
-- |
29.9321666000, 78.8728888000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3148]
Lakholi Ubot Gawani motor road to Devradi Devi Saidiyakhal motor Road
|
Scupper |
8.100
|
-- |
29.9302500000, 78.8934916700 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
10.000
|
-- |
29.8785320000, 78.8526470000 |
Estimation Done |
5 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
10.200
|
-- |
29.8769460000, 78.8534160000 |
Estimation Done |
8 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
10.440
|
-- |
29.8763520000, 78.8539670000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
10.515
|
-- |
29.8769860000, 78.8537200000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
10.750
|
-- |
29.8790120000, 78.8533150000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
10.901
|
-- |
29.8796920000, 78.8545050000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
11.059
|
-- |
29.8807470000, 78.8551700000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
11.119
|
-- |
29.8811120000, 78.8556280000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
11.352
|
-- |
29.8823620000, 78.8571450000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
11.493
|
-- |
29.8818530000, 78.8576840000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
11.580
|
-- |
29.8801470000, 78.8587880000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
11.704
|
-- |
29.8812080000, 78.8583440000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
13.128
|
-- |
29.8794540000, 78.8591600000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
13.290
|
-- |
29.8793460000, 78.8604730000 |
Identified |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
13.526
|
-- |
29.8775890000, 78.8610890000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
13.762
|
-- |
29.8770450000, 78.8667270000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
13.973
|
-- |
29.8779810000, 78.8687070000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
14.220
|
-- |
29.8777950000, 78.8686680000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
14.467
|
-- |
29.8774950000, 78.8683880000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
14.581
|
-- |
29.8758050000, 78.8683580000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
14.695
|
-- |
29.8740200000, 78.8673900000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
14.809
|
-- |
29.8734040000, 78.8664330000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
14.934
|
-- |
29.8723880000, 78.8662350000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
15.000
|
-- |
29.8723560000, 78.8661110000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
15.111
|
-- |
29.8733110000, 78.8660770000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
15.241
|
-- |
29.8742550000, 78.8668160000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
15.381
|
-- |
29.8743030000, 78.8666570000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
15.455
|
-- |
29.8737780000, 78.8662090000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
15.634
|
-- |
29.8723030000, 78.8655470000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
15.786
|
-- |
29.8718630000, 78.8655280000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
15.856
|
-- |
29.8724340000, 78.8652870000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
15.924
|
-- |
29.8729510000, 78.8651360000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
16.116
|
-- |
29.8720250000, 78.8634980000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
16.217
|
-- |
29.8718420000, 78.8625600000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
16.538
|
-- |
29.8721490000, 78.8600270000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
16.747
|
-- |
29.8703480000, 78.8603330000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
16.873
|
-- |
29.8692480000, 78.8605150000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
17.213
|
-- |
29.8665370000, 78.8600370000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
17.363
|
-- |
29.8652350000, 78.8596200000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
17.453
|
-- |
29.8645370000, 78.8592620000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
17.713
|
-- |
29.8639490000, 78.8592370000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
17.773
|
-- |
29.8643560000, 78.8593610000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3149]
Sanglakoti Bhaindgauv Gutincha Tilkholi Jajedi motor road
|
Scupper |
17.823
|
-- |
29.8639710000, 78.8590620000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3151]
Sapla Bend to Pali road
|
Scupper |
0.100
|
-- |
30.2132550000, 78.7302500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3151]
Sapla Bend to Pali road
|
Scupper |
0.375
|
-- |
30.2139666000, 78.7280861000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3151]
Sapla Bend to Pali road
|
Scupper |
0.425
|
-- |
30.2138250000, 78.7274055500 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3151]
Sapla Bend to Pali road
|
Scupper |
0.500
|
-- |
30.2139305000, 78.7267027000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3151]
Sapla Bend to Pali road
|
Scupper |
0.550
|
-- |
30.2145110000, 78.7264666000 |
Sanctioned |
4 |
|
|
|
|
Jan 2024 |
[3151]
Sapla Bend to Pali road
|
Scupper |
0.625
|
-- |
30.2145880000, 78.7259972000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3151]
Sapla Bend to Pali road
|
Scupper |
0.850
|
-- |
30.2150770000, 78.7238610000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3151]
Sapla Bend to Pali road
|
Scupper |
1.075
|
-- |
30.2150940000, 78.7226138000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3151]
Sapla Bend to Pali road
|
Scupper |
1.175
|
-- |
30.2148020000, 78.7237472000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3156]
Dhartoli motor road
|
Scupper |
0.100
|
-- |
29.9289440000, 78.8776250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3156]
Dhartoli motor road
|
Scupper |
0.220
|
-- |
29.9286527000, 78.8786700000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3156]
Dhartoli motor road
|
Scupper |
0.530
|
-- |
29.9283630000, 78.8793100000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3156]
Dhartoli motor road
|
Scupper |
0.787
|
-- |
29.9290861000, 78.8810000000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3156]
Dhartoli motor road
|
Scupper |
0.860
|
-- |
29.9292055000, 78.8805190000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3156]
Dhartoli motor road
|
Scupper |
0.944
|
-- |
29.9292770000, 78.8804580000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3160]
Giwali Bheti motor raod
|
Scupper |
0.100
|
-- |
29.9510470000, 78.8902550000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3160]
Giwali Bheti motor raod
|
Scupper |
0.200
|
-- |
29.9510470000, 78.8905500000 |
Estimation Done |
0 |
|
|
|
|
Aug 2024 |
[3161]
Road from km 1 of village Kandi to Tolyu
|
Scupper |
0.070
|
-- |
30.1935944000, 78.6563380000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3161]
Road from km 1 of village Kandi to Tolyu
|
Scupper |
0.225
|
-- |
30.1936416000, 78.6551361000 |
Estimation Done |
4 |
|
|
|
|
Aug 2024 |
[3162]
Junior High School Doob to Kaldung motor road
|
Scupper |
0.000
|
-- |
30.1517380000, 78.8018861000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3162]
Junior High School Doob to Kaldung motor road
|
Scupper |
0.085
|
-- |
30.1512160000, 78.8021940000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3162]
Junior High School Doob to Kaldung motor road
|
Scupper |
0.325
|
-- |
30.1510916000, 78.8031160000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3164]
Kathuli to Sediyakhal motor road
|
Scupper |
0.230
|
-- |
29.9199500000, 78.9027500000 |
Treatment in Progress |
5 |
2019-02-05 00:00:00 |
2022-05-05 00:00:00 |
1 |
ok |
Aug 2024 |
[3164]
Kathuli to Sediyakhal motor road
|
Scupper |
0.375
|
-- |
29.9191380000, 78.9016800000 |
Treatment in Progress |
4 |
2019-02-05 00:00:00 |
2022-05-05 00:00:00 |
1 |
ok |
Aug 2024 |
[3164]
Kathuli to Sediyakhal motor road
|
Scupper |
0.528
|
-- |
29.9182527700, 78.9009972000 |
Treatment in Progress |
4 |
2019-02-10 00:00:00 |
2022-05-18 00:00:00 |
1 |
Ok |
Aug 2024 |
[3164]
Kathuli to Sediyakhal motor road
|
Scupper |
0.595
|
-- |
29.9177080000, 78.9006583000 |
Treatment in Progress |
4 |
2019-02-12 00:00:00 |
2022-05-05 00:00:00 |
1 |
Ok |
Aug 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
0.097
|
-- |
29.8980970000, 78.9125400000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
0.173
|
-- |
29.8976250000, 78.9119777700 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
0.230
|
-- |
29.8976722000, 78.9115277000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
0.354
|
-- |
29.8974000000, 78.9105333300 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
0.503
|
-- |
29.8971222200, 78.9094166000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
0.654
|
-- |
29.8971694000, 78.9081888000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
0.780
|
-- |
29.8970027000, 78.9082583000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
0.969
|
-- |
29.8968277000, 78.9084444000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
1.170
|
-- |
29.8967722200, 78.9102472200 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
1.370
|
-- |
29.8966166000, 78.9122305000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
1.500
|
-- |
29.8965083300, 78.9125305000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
1.680
|
-- |
29.8963777700, 78.9126527000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
1.780
|
-- |
29.8969220000, 78.9133250000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
1.900
|
-- |
29.8968861000, 78.9143970000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Scupper |
1.980
|
-- |
29.8969722000, 78.9150472000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Parapet |
0.081 - 0.108
|
27.000 |
29.8982666000, 78.9125472000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Parapet |
0.097 - 0.101
|
4.000 |
29.8980970000, 78.9125400000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Parapet |
0.173 - 0.185
|
12.000 |
29.8976250000, 78.9119770000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[3166]
Pokhra to village Bhadoli motor road
|
Parapet |
0.230 - 0.259
|
29.000 |
29.8976722000, 78.9115277000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[5817]
Link road for village Talli Airoli
|
Scupper |
0.050
|
-- |
29.9311111100, 78.9091666700 |
Estimation Done |
0 |
2022-02-03 00:00:00 |
2024-03-13 00:00:00 |
1 |
ok |
Aug 2024 |
[5817]
Link road for village Talli Airoli
|
Scupper |
0.375
|
-- |
29.9330555600, 78.9086111100 |
Estimation Done |
4 |
2022-02-03 00:00:00 |
2024-03-12 00:00:00 |
1 |
ok |
Aug 2024 |
[5817]
Link road for village Talli Airoli
|
Scupper |
0.600
|
-- |
29.9350000000, 78.9100000000 |
Estimation Done |
4 |
2022-02-03 00:00:00 |
2024-03-13 00:00:00 |
1 |
ok |
Aug 2024 |
[5818]
Road from Kamalpur inter collage to Sanglakoti suspension bridge
|
Scupper |
0.325
|
-- |
29.9005350000, 78.8547660000 |
Estimation Done |
4 |
2023-11-05 00:00:00 |
|
0 |
ok |
Aug 2024 |
[5818]
Road from Kamalpur inter collage to Sanglakoti suspension bridge
|
Scupper |
0.575
|
-- |
29.9039320000, 78.8512720000 |
Estimation Done |
4 |
2023-11-15 00:00:00 |
|
0 |
ok |
Aug 2024 |
[5818]
Road from Kamalpur inter collage to Sanglakoti suspension bridge
|
Parapet |
0.325 - 0.329
|
4.000 |
29.9005350000, 78.8547660000 |
Estimation Done |
4 |
2023-11-10 00:00:00 |
|
0 |
ok |
Aug 2024 |
[5818]
Road from Kamalpur inter collage to Sanglakoti suspension bridge
|
Parapet |
0.575 - 0.579
|
4.000 |
29.9039320000, 78.8512720000 |
Estimation Done |
4 |
2023-11-18 00:00:00 |
|
|
ok |
Aug 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Scupper |
0.029
|
-- |
30.1989050000, 78.6870720000 |
Estimation Done |
5 |
|
|
|
|
Jan 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Scupper |
0.175
|
-- |
30.1987416000, 78.6870600000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Scupper |
0.270
|
-- |
30.1986305000, 78.6870500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Scupper |
0.525
|
-- |
30.1875400000, 78.6893500000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Scupper |
0.550
|
-- |
30.1998130000, 78.6895700000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Scupper |
0.900
|
-- |
30.2021027000, 78.6909130000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Scupper |
0.950
|
-- |
30.2022944000, 78.6915638000 |
Estimation Done |
4 |
|
|
|
|
Jan 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Parapet |
0.050 - 0.060
|
10.000 |
30.1991350000, 78.6867590000 |
Estimation Done |
7 |
2023-11-05 00:00:00 |
2023-11-29 00:00:00 |
1 |
ok |
Aug 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Parapet |
0.175 - 0.181
|
6.000 |
30.1988110000, 78.6871230000 |
Identified |
8 |
2023-11-05 00:00:00 |
2023-12-05 00:00:00 |
1 |
ok |
Aug 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Parapet |
0.450 - 0.461
|
11.300 |
30.1993440000, 78.6884560000 |
Identified |
7 |
2023-11-16 00:00:00 |
2023-12-05 00:00:00 |
1 |
ok |
Aug 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Parapet |
0.650 - 0.664
|
14.400 |
30.2007160000, 78.6892420000 |
Identified |
7 |
2023-11-05 00:00:00 |
2023-12-21 00:00:00 |
|
Ok |
Aug 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Parapet |
0.725 - 0.731
|
6.000 |
30.2014540000, 78.6901260000 |
Identified |
6 |
2023-11-23 00:00:00 |
2023-12-08 00:00:00 |
1 |
ok |
Aug 2024 |
[5820]
Kamarghar Dehalchori motor road to Panchur
|
Parapet |
0.850 - 0.862
|
11.600 |
30.2020910000, 78.6908360000 |
Identified |
8 |
2023-11-27 00:00:00 |
2023-12-23 00:00:00 |
1 |
Ok |
Aug 2024 |
[9176]
Road from sapla band pali to manjakot motor road
|
Scupper |
0.200
|
-- |
30.2146694400, 78.7239111100 |
Estimation Done |
8 |
2018-02-03 00:00:00 |
|
0 |
|
Aug 2024 |
[9176]
Road from sapla band pali to manjakot motor road
|
Scupper |
0.400
|
-- |
30.2153583300, 78.7218444400 |
Estimation Done |
8 |
2018-02-22 00:00:00 |
|
0 |
|
Aug 2024 |
[9177]
Kulashu motor road
|
Scupper |
0.300
|
-- |
30.1804694400, 78.6458055600 |
Identified |
7 |
|
|
0 |
Reqired |
Aug 2024 |
[9177]
Kulashu motor road
|
Scupper |
0.420
|
-- |
30.1806861100, 78.6461277800 |
Estimation Done |
7 |
|
|
|
ok |
Aug 2024 |
[9177]
Kulashu motor road
|
Scupper |
0.470
|
-- |
30.1807944400, 78.6466083300 |
Estimation Done |
7 |
|
|
0 |
ok |
Aug 2024 |
[9177]
Kulashu motor road
|
Parapet |
0.480 - 0.493
|
12.500 |
30.1808190000, 78.6468540000 |
Estimation Done |
6 |
2020-07-08 00:00:00 |
2021-09-12 00:00:00 |
1 |
ok |
Aug 2024 |
[5819]
Road from Kirtinagar Kulasu motor Road towards Kulasu
|
Parapet |
0.000 - 0.016
|
16.000 |
30.1807250000, 78.6470250000 |
Estimation Done |
7 |
2020-07-15 00:00:00 |
2020-07-31 00:00:00 |
1 |
ok |
Aug 2024 |