SRMD

Financial Analysis

All amounts in ₹ Lacs

Starting Balance

16.43

Balance Cost at Start of FY

New Works


No New Work this year

Savings

0.00

No Savings

Final Spillover Calculation

16.43

Resultant Spillover Amount

As Planned in Works

Month Target Achivement
Apr, 2025 0 0
May, 2025 0 0
Jun, 2025 0 0
Jul, 2025 0 0
Aug, 2025 0 0
Sep, 2025 0 0
Oct, 2025 0 0
Nov, 2025 0 0
Dec, 2025 0 0
Jan, 2026 0 0
Feb, 2026 0 0
Mar, 2026 0 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 0 0 0
May, 2025 0 0 0
Jun, 2025 0 0 0
Jul, 2025 1.5 10.5 0
Aug, 2025 8 21 0
Sep, 2025 16 42 0
Oct, 2025 24 63 0
Nov, 2025 32 152 0
Dec, 2025 63 241 0
Jan, 2026 114 326 0
Feb, 2026 160 418 0
Mar, 2026 200 418 0

Instant Demand

Cummulative Demand
Up to Oct-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

IFMS Payments