SRMD

Balance Cost at Start of Fy : 13482.01 Lacs. New Works Sanctioned in This Fy: 49 No of Rs 1958.53 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 295.18 17.88
Jun, 2024 455.52 84.6
Jul, 2024 510.23 84.67
Aug, 2024 539.23 285.46
Sep, 2024 726.62 487.42
Oct, 2024 761.62 581.74
Nov, 2024 816.46 581.94
Dec, 2024 881.46 581.94
Jan, 2025 881.46 581.94
Feb, 2025 959.53 581.94
Mar, 2025 959.53 581.94

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 0 0 20.86
Dec, 2024 0 32.45 20.86
Jan, 2025 0 56.78 20.86
Feb, 2025 0 81.12 20.86
Mar, 2025 0 81.12 20.86

Instant Demand

Cummulative Demand
Up to Nov-2024

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

IFMS Payments

2024-07-26 7.12
2024-10-28 20.86