SRMD

Balance Cost at Start of Fy : 5544.92 Lacs. New Works Sanctioned in This Fy: 2 No of Rs 57.01 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 10 43.19
May, 2024 100.46 261.97
Jun, 2024 213.07 472.23
Jul, 2024 617.66 598.19
Aug, 2024 989.75 737.33
Sep, 2024 1204.96 979.13
Oct, 2024 1726.06 1375.9
Nov, 2024 2069.19 1449.1
Dec, 2024 2302.51 1449.1
Jan, 2025 2342.4 1449.1
Feb, 2025 2479.89 1449.1
Mar, 2025 3457.99 1449.1

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 0 0 27
Dec, 2024 0 37 27
Jan, 2025 0 63.5 27
Feb, 2025 0 90 27
Mar, 2025 0 90 27

Instant Demand

Cummulative Demand
Up to Nov-2024

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

IFMS Payments