SRMD

Balance Cost at Start of Fy : 7488.61 Lacs. New Works Sanctioned in This Fy: 36 No of Rs 133.41 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 16.65
May, 2024 12.4 33.76
Jun, 2024 74.76 282.5
Jul, 2024 93.26 359.31
Aug, 2024 233.94 359.31
Sep, 2024 352.23 359.31
Oct, 2024 402.23 359.31
Nov, 2024 511.47 359.31
Dec, 2024 711.91 359.31
Jan, 2025 851.91 359.31
Feb, 2025 1031.01 359.31
Mar, 2025 1234.17 359.31

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 10 0 0
Dec, 2024 20 0 0
Jan, 2025 30 0 0
Feb, 2025 35 0 0
Mar, 2025 35 0 0

Instant Demand

Cummulative Demand
Up to Aug-2024

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00