Balance Cost at Start of Fy : 1316.87 Lacs. New Works Sanctioned in This Fy: 16 No of Rs 175 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 28.13
May, 2024 79 131.33
Jun, 2024 285.15 187.71
Jul, 2024 432.04 274.27
Aug, 2024 472.04 284.74
Sep, 2024 518.16 351.33
Oct, 2024 538.16 356.31
Nov, 2024 548.71 356.31
Dec, 2024 548.71 356.31
Jan, 2025 548.71 356.31
Feb, 2025 548.71 356.31
Mar, 2025 548.71 356.31

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 0 0 0
Dec, 2024 0 9 0
Jan, 2025 0 16 0
Feb, 2025 0 23 0
Mar, 2025 0 23 0

Instant Demand

Cummulative Demand
Up to Nov-2024

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

IFMS Payments