SRMD

Balance Cost at Start of Fy : 2256.73 Lacs. New Works Sanctioned in This Fy: 26 No of Rs 476 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 50 231.9
Jun, 2024 140 408.63
Jul, 2024 172 531.35
Aug, 2024 193 666.47
Sep, 2024 259.88 760.51
Oct, 2024 456.88 828.77
Nov, 2024 529.38 830.02
Dec, 2024 553.88 830.02
Jan, 2025 578.88 830.02
Feb, 2025 742.61 830.02
Mar, 2025 1024.11 830.02

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 0 0 0
Dec, 2024 0 28 0
Jan, 2025 0 48 0
Feb, 2025 0 68 0
Mar, 2025 0 68 0

Instant Demand

Cummulative Demand
Up to Nov-2024

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

IFMS Payments