SRMD

Balance Cost at Start of Fy : 1218.98 Lacs. New Works Sanctioned in This Fy: 9 No of Rs 132 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 110 583.74
Jun, 2024 206.54 643.3
Jul, 2024 293.13 651.78
Aug, 2024 342.15 746.91
Sep, 2024 388.75 806.45
Oct, 2024 423.75 806.45
Nov, 2024 452.02 806.45
Dec, 2024 472.02 806.45
Jan, 2025 495.17 806.45
Feb, 2025 495.17 806.45
Mar, 2025 495.17 806.45

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 0 0 0
Dec, 2024 0 22 0
Jan, 2025 0 39 0
Feb, 2025 0 56 0
Mar, 2025 0 56 0