Balance Cost at Start of Fy : 2613.57 Lacs. New Works Sanctioned in This Fy: 39 No of Rs 177 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 167.17 51.27
Jun, 2024 631.88 146.8
Jul, 2024 734 237.7
Aug, 2024 734 359.87
Sep, 2024 739 368.25
Oct, 2024 814 500.21
Nov, 2024 897 504.62
Dec, 2024 955 504.62
Jan, 2025 980 504.62
Feb, 2025 1004 504.62
Mar, 2025 1031.36 504.62

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 0 0 0
Dec, 2024 0 11 0
Jan, 2025 0 19 0
Feb, 2025 0 27 0
Mar, 2025 0 27 0

Instant Demand

Cummulative Demand
Up to Nov-2024

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

IFMS Payments