Balance Cost at Start of Fy : 4095.44 Lacs. New Works Sanctioned in This Fy: 47 No of Rs 310.33 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 312.23 314.72
May, 2024 818.78 665.31
Jun, 2024 1194.8 926.62
Jul, 2024 1288.81 1218.19
Aug, 2024 1401.45 1221.86
Sep, 2024 1688.21 1221.86
Oct, 2024 2063.73 1221.86
Nov, 2024 2215.82 1221.86
Dec, 2024 2416.32 1221.86
Jan, 2025 2594.7 1221.86
Feb, 2025 2926.52 1221.86
Mar, 2025 3086.55 1221.86

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 0 0 0
Dec, 2024 0 0 0
Jan, 2025 0 0 0
Feb, 2025 0 0 0
Mar, 2025 0 0 0

Instant Demand

Cummulative Demand
Up to Aug-2024

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

IFMS Payments