SRMD

Balance Cost at Start of Fy : 2178.46 Lacs. New Works Sanctioned in This Fy: 2 No of Rs 153.31 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 423.24 573.41
Jun, 2024 1030.58 857.49
Jul, 2024 1382.61 929.97
Aug, 2024 1509.52 1092.56
Sep, 2024 1635.9 1154.74
Oct, 2024 2012.4 1154.74
Nov, 2024 2227.75 1154.74
Dec, 2024 2367.27 1154.74
Jan, 2025 2490.98 1154.74
Feb, 2025 2545.51 1154.74
Mar, 2025 2629.07 1154.74

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 0 0 0
Dec, 2024 0 11 0
Jan, 2025 0 18 0
Feb, 2025 0 25 0
Mar, 2025 0 25 0

Instant Demand

Cummulative Demand
Up to Nov-2024

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00