केन्द्रीय सड़क अवसंरचना निधि (सी0आर0आई0एफ0)
All amounts in ₹ Lacs
Balance Cost at Start of FY
No Savings
Resultant Spillover Amount
As Planned in Works
| Month | Target | Achivement |
|---|---|---|
| Apr, 2025 | 0 | 0 |
| May, 2025 | 100 | 617.81 |
| Jun, 2025 | 1400 | 1356.16 |
| Jul, 2025 | 1400 | 1589.96 |
| Aug, 2025 | 1400 | 1665.04 |
| Sep, 2025 | 1400 | 1824.42 |
| Oct, 2025 | 2285.23 | 1902.67 |
| Nov, 2025 | 2285.23 | 1902.67 |
| Dec, 2025 | 2285.23 | 1902.67 |
| Jan, 2026 | 2285.23 | 1902.67 |
| Feb, 2026 | 2285.23 | 1902.67 |
| Mar, 2026 | 2285.23 | 1902.67 |
Financial Target/ Achivement
| Month |
Annual Demand |
Target By HQ |
Achivement |
|---|---|---|---|
| Apr, 2025 | 0 | 1.22 | 0 |
| May, 2025 | 100 | 1143.22 | 524.83 |
| Jun, 2025 | 1400 | 2285.22 | 1356.17 |
| Jul, 2025 | 1400 | 2285.22 | 1589.97 |
| Aug, 2025 | 1400 | 2285.22 | 1665.04 |
| Sep, 2025 | 1400 | 2285.22 | 1824.42 |
| Oct, 2025 | 2285.23 | 2285.22 | 1902.68 |
| Nov, 2025 | 2285.23 | 2285.22 | 1903.47 |
| Dec, 2025 | 2285.23 | 2285.22 | 1903.47 |
| Jan, 2026 | 2285.23 | 2285.22 | 1903.47 |
| Feb, 2026 | 2285.23 | 2285.22 | 1903.47 |
| Mar, 2026 | 2285.23 | 2285.22 | 1903.47 |
Instant Demand
Cummulative Demand
Up to Nov-2025
0 Lacs
History (in Reverse Order)
Allotment
Cummulative Allotment
2285.22 Lacs
History (in Reverse Order)
IFMS Payments