सड़क सुरक्षा कार्य

Balance Cost at Start of Fy : 942.12 Lacs. New Works Sanctioned in This Fy: 1 No of Rs 571.33 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 10 0
Jul, 2024 110 134.9
Aug, 2024 210 134.9
Sep, 2024 310 134.9
Oct, 2024 560 134.9
Nov, 2024 810 134.9
Dec, 2024 910 134.9
Jan, 2025 1010 134.9
Feb, 2025 1110 134.9
Mar, 2025 1311.49 134.9

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 10 0 0
May, 2024 85 0 0
Jun, 2024 160 0 0
Jul, 2024 240 0 134.9
Aug, 2024 340 0 134.9
Sep, 2024 440 0 134.9
Oct, 2024 540 0 289.89
Nov, 2024 680 0 289.89
Dec, 2024 780 0 289.89
Jan, 2025 980 0 289.89
Feb, 2025 1130 0 289.89
Mar, 2025 1311.59 0 289.89

Instant Demand

Cummulative Demand
Up to Nov-2024

0 Lacs

History (in Reverse Order)

01 Apr 2024 0.00

Allotment

Cummulative Allotment

410.00 Lacs

History (in Reverse Order)

19 Nov 2024 410.00
23 Oct 2024 290.00
31 Aug 2024 210.00
20 May 2024 160.00
01 Apr 2024 0.00

IFMS Payments

2024-07-09 134.90
2024-09-06 209.90
2024-10-29 289.90