सड़क सुरक्षा कार्य

Financial Analysis

All amounts in ₹ Lacs

Starting Balance

196.18

Balance Cost at Start of FY

New Works


No New Work this year

Savings

0.00

No Savings

Final Spillover Calculation

196.18

Resultant Spillover Amount

As Planned in Works

Month Target Achivement
Apr, 2025 0 0
May, 2025 0 0
Jun, 2025 35 0
Jul, 2025 70 4.97
Aug, 2025 95 4.97
Sep, 2025 125 4.97
Oct, 2025 150 4.97
Nov, 2025 170 4.97
Dec, 2025 189.48 4.97
Jan, 2026 196.18 4.97
Feb, 2026 196.18 4.97
Mar, 2026 196.18 4.97

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 0 0 0
May, 2025 0 0 0
Jun, 2025 35 0 0
Jul, 2025 70 0 0
Aug, 2025 95 0 0
Sep, 2025 125 0 0
Oct, 2025 150 0 0
Nov, 2025 170 0 0
Dec, 2025 189.48 0 0
Jan, 2026 196.18 0 0
Feb, 2026 196.18 0 0
Mar, 2026 196.18 0 0

Instant Demand

Cummulative Demand
Up to Aug-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

60.64 Lacs

History (in Reverse Order)

02 May 2025 60.64
01 Apr 2025 0.00

IFMS Payments

2025-07-25 2.49
2025-07-29 4.97
2025-08-08 12.42
2025-08-18 17.39