सड़क सुरक्षा कार्य

Balance Cost at Start of Fy : 377.30 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 0 0
Jul, 2024 27 0
Aug, 2024 126 0
Sep, 2024 225 0
Oct, 2024 294 0
Nov, 2024 331.29 0
Dec, 2024 358.89 0
Jan, 2025 377.3 0
Feb, 2025 377.3 0
Mar, 2025 377.3 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 0 0 0
Nov, 2024 0 0 0
Dec, 2024 0 0 0
Jan, 2025 0 0 0
Feb, 2025 0 0 0
Mar, 2025 0 0 0

Instant Demand

Cummulative Demand
Up to Nov-2024

377.30 Lacs

History (in Reverse Order)

09 Nov 2024 377.30
30 May 2024 1.00
15 May 2024 377.30
01 Apr 2024 0.00

Allotment

Cummulative Allotment

300.00 Lacs

History (in Reverse Order)

19 Nov 2024 300.00
01 Apr 2024 0.00