Balance Cost at Start of Fy : 1224.96 Lacs.

सड़क सुरक्षा कार्य

As Planned in Works

(Cumulative in Rs Lacs.)

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 0 0
Jul, 2024 0 0
Aug, 2024 200 0
Sep, 2024 500 0
Oct, 2024 700 0
Nov, 2024 900 0
Dec, 2024 1089.68 0
Jan, 2025 1189.68 0
Feb, 2025 1224.96 0
Mar, 2025 1224.96 0

Financial Target/ Achivement

(Cumulative in Rs Lacs.)

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 0 0 0
Aug, 2024 0 0 0
Sep, 2024 0 0 0
Oct, 2024 500 0 0
Nov, 2024 500 0 0
Dec, 2024 724.96 0 0
Jan, 2025 724.96 0 0
Feb, 2025 1224.96 0 0
Mar, 2025 1224.96 0 0

Instant Demand History

Cumulative Demand for Next Three Months at a Particular Date

(Cumulative in Rs Lacs.)

01 Apr 2024 0.00
09 May 2024 1,224.96
25 May 2024 0.01
30 Jun 2024 0.01

Allotment History

(Cumulative in Rs Lacs.)

01 Apr 2024 0.00
30 Jun 2024 0.00

IFMS Payments

(Cumulative in Rs Lacs.)