चालू निर्माण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 13091.87 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 0 0
Jul, 2024 0 0
Aug, 2024 0 0
Sep, 2024 0 0
Oct, 2024 0 0
Nov, 2024 0 0
Dec, 2024 0 0
Jan, 2025 0 0
Feb, 2025 0 0
Mar, 2025 0 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 15.82 0 15.82
May, 2024 212.23 188.67 407.6
Jun, 2024 554.97 555.63 905.2
Jul, 2024 986.61 1099.41 1379.98
Aug, 2024 1436.67 1719.08 1676.6
Sep, 2024 2035.42 3052.05 2482.95
Oct, 2024 2540.28 3674.44 2704.99
Nov, 2024 2957.47 4070.88 3214.81
Dec, 2024 3695.26 4484.36 4150.73
Jan, 2025 4837.91 4904.42 4924.8
Feb, 2025 6312.15 5811.09 5649.94
Mar, 2025 6613.66 5761.09 6081.62

Instant Demand

Cummulative Demand
Up to Apr-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

IFMS Payments