चालू निर्माण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 16448.09 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 0 0
Jul, 2024 0 0
Aug, 2024 0 0
Sep, 2024 0 0
Oct, 2024 0 0
Nov, 2024 0 0
Dec, 2024 0 0
Jan, 2025 0 0
Feb, 2025 0 0
Mar, 2025 0 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 1258.84 1179.14 1729.89
Jun, 2024 1852.74 1942.98 2384.61
Jul, 2024 2837.15 2946.23 3141.76
Aug, 2024 3745.76 3984.29 3684.35
Sep, 2024 5086.29 5816.14 5234.02
Oct, 2024 5928.48 6706.15 5696.5
Nov, 2024 6755.71 7669.52 6319.39
Dec, 2024 8294.57 8555.36 7498.59
Jan, 2025 9646.37 9287.09 8538.47
Feb, 2025 10879.88 10948.64 9968.15
Mar, 2025 11215.99 10948.63 10788.15

Instant Demand

Cummulative Demand
Up to Apr-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

IFMS Payments