चालू निर्माण कार्य-राज्य सैक्टर
All amounts in ₹ Lacs
Balance Cost at Start of FY
Works
Sanctioned
Spent
Saving in Works
Resultant Spillover Amount
As Planned in Works
Month | Target | Achivement |
---|---|---|
Apr, 2025 | 0 | 0 |
May, 2025 | 26.07 | 35.07 |
Jun, 2025 | 81.52 | 52.85 |
Jul, 2025 | 123.28 | 82.85 |
Aug, 2025 | 149.54 | 116.1 |
Sep, 2025 | 185.2 | 116.1 |
Oct, 2025 | 191.4 | 116.1 |
Nov, 2025 | 222.4 | 116.1 |
Dec, 2025 | 272.4 | 116.1 |
Jan, 2026 | 356.46 | 116.1 |
Feb, 2026 | 366.46 | 116.1 |
Mar, 2026 | 366.46 | 116.1 |
Financial Target/ Achivement
Month |
Annual Demand |
Target By HQ |
Achivement |
---|---|---|---|
Apr, 2025 | 0 | 36.57 | 0 |
May, 2025 | 32.07 | 91.42 | 32.77 |
Jun, 2025 | 70.82 | 146.27 | 85 |
Jul, 2025 | 122.82 | 164.55 | 114 |
Aug, 2025 | 157.08 | 182.83 | 114 |
Sep, 2025 | 171.74 | 219.4 | 114 |
Oct, 2025 | 176.74 | 255.97 | 114 |
Nov, 2025 | 187.74 | 292.54 | 114 |
Dec, 2025 | 282.74 | 310.82 | 114 |
Jan, 2026 | 366.46 | 329.1 | 114 |
Feb, 2026 | 366.46 | 365.69 | 114 |
Mar, 2026 | 366.46 | 365.69 | 114 |
Instant Demand
Cummulative Demand
Up to Aug-2025
0 Lacs
History (in Reverse Order)
Allotment
Cummulative Allotment
183.02 Lacs
History (in Reverse Order)
IFMS Payments