चालू निर्माण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 2465.24 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2025 0 0
May, 2025 0 0
Jun, 2025 30 0
Jul, 2025 35 0
Aug, 2025 35 0
Sep, 2025 35 0
Oct, 2025 35 0
Nov, 2025 40 0
Dec, 2025 45 0
Jan, 2026 45 0
Feb, 2026 45 0
Mar, 2026 45 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 0 0 0
May, 2025 0 0 0
Jun, 2025 0 0 0
Jul, 2025 0 0 0
Aug, 2025 0 0 0
Sep, 2025 0 0 0
Oct, 2025 0 0 0
Nov, 2025 0 0 0
Dec, 2025 0 0 0
Jan, 2026 0 0 0
Feb, 2026 0 0 0
Mar, 2026 0 0 0

Instant Demand

Cummulative Demand
Up to Apr-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

IFMS Payments