चालू निर्माण कार्य-राज्य सैक्टर

Financial Analysis

All amounts in ₹ Lacs

Starting Balance

2,111.30

Balance Cost at Start of FY

New Works

3

Works

1,012.98

Sanctioned

0.00

Spent

Savings

0.00

No Savings

Final Spillover Calculation

2,111.30 + 1,012.98 = 3,124.28

Resultant Spillover Amount

As Planned in Works

Month Target Achivement
Apr, 2025 0 0
May, 2025 32 0.5
Jun, 2025 110.1 60.76
Jul, 2025 151.1 109.55
Aug, 2025 175.1 112.21
Sep, 2025 220.1 114.05
Oct, 2025 327.1 114.05
Nov, 2025 484.1 114.05
Dec, 2025 634.1 114.05
Jan, 2026 816 114.05
Feb, 2026 952 114.05
Mar, 2026 952 114.05

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 0 51.21 0
May, 2025 32 128.02 0.5
Jun, 2025 111.1 204.83 60.76
Jul, 2025 154.5 230.43 109.55
Aug, 2025 181.5 256.03 113.73
Sep, 2025 231.5 407.03 113.73
Oct, 2025 283.5 558.03 113.73
Nov, 2025 483.5 609.24 113.73
Dec, 2025 763.5 634.84 113.73
Jan, 2026 963.5 760.84 113.73
Feb, 2026 1011.84 1011.84 113.73
Mar, 2026 1011.84 1011.84 113.73

Instant Demand

Cummulative Demand
Up to Sep-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

256.00 Lacs

History (in Reverse Order)

31 Jul 2025 256.00
30 Apr 2025 110.00
01 Apr 2025 0.00

IFMS Payments

2025-05-29 0.50
2025-06-05 10.02
2025-06-20 17.03
2025-06-24 17.34
2025-06-30 60.76
2025-07-07 61.13
2025-07-09 63.04
2025-07-14 64.66
2025-07-23 83.41
2025-07-25 109.55
2025-08-08 109.70
2025-08-14 110.38
2025-08-22 112.14
2025-08-28 112.21
2025-09-01 112.46
2025-09-09 114.29