चालू निर्माण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 3963.68 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 0 0
Jul, 2024 0 0
Aug, 2024 0 0
Sep, 2024 0 0
Oct, 2024 0 0
Nov, 2024 0 0
Dec, 2024 0 0
Jan, 2025 0 0
Feb, 2025 0 0
Mar, 2025 0 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 12.74 52 52.64
Jun, 2024 34.96 100 74.02
Jul, 2024 113.09 124 199.41
Aug, 2024 113.87 174 199.99
Sep, 2024 173.65 274 350
Oct, 2024 184.2 274 350
Nov, 2024 184.2 285 370.81
Dec, 2024 195.49 298 382.3
Jan, 2025 268.24 318 425.14
Feb, 2025 416.76 392 500.62
Mar, 2025 587 392 587

Instant Demand

Cummulative Demand
Up to Apr-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

IFMS Payments