Starting Balance

3,229.11

Balance Cost at Start of FY

New Works

21

Works

2,059.08

Sanctioned

0.00

Spent

Savings

0.00

No Savings

Final Spillover Calculation

3,229.11 + 2,059.08 = 5,288.19

Resultant Spillover Amount

As Planned in Works

Month Target Achivement
Apr, 2025 180 0
May, 2025 610 542.7
Jun, 2025 828 754.5
Jul, 2025 1059 963.24
Aug, 2025 1276 997.25
Sep, 2025 1446.4 997.25
Oct, 2025 1552.4 997.25
Nov, 2025 1903.9 997.25
Dec, 2025 2055.9 997.25
Jan, 2026 2155.9 997.25
Feb, 2026 2602.4 997.25
Mar, 2026 2602.4 997.25

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 218.48 218.48 83.92
May, 2025 546.2 546.2 542.7
Jun, 2025 873.92 873.92 874.97
Jul, 2025 983.16 983.16 985.6
Aug, 2025 1092.4 1092.4 1039.15
Sep, 2025 1346.4 1346.4 1039.15
Oct, 2025 1600.4 1600.4 1039.15
Nov, 2025 1854.4 1854.4 1039.15
Dec, 2025 1981.4 1981.4 1039.15
Jan, 2026 2108.4 2108.4 1039.15
Feb, 2026 2361.4 2361.4 1039.15
Mar, 2026 2361.4 2361.4 1039.15

Instant Demand

Cummulative Demand
Up to Aug-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

1255.00 Lacs

History (in Reverse Order)

31 Jul 2025 1,255.00
15 Jul 2025 1,105.00
26 Jun 2025 875.00
30 Apr 2025 760.00
01 Apr 2025 0.00

IFMS Payments

2025-05-01 79.91
2025-05-07 111.78
2025-05-09 141.94
2025-05-14 158.21
2025-05-15 182.86
2025-05-16 236.40
2025-05-19 238.75
2025-05-20 240.69
2025-05-21 247.89
2025-05-22 252.28
2025-05-23 266.77
2025-05-26 299.73
2025-05-28 327.87
2025-05-30 510.97
2025-05-31 542.68
2025-06-06 571.87
2025-06-12 658.11
2025-06-16 658.47
2025-06-19 675.80
2025-06-24 706.93
2025-06-25 710.82
2025-06-30 754.48
2025-07-01 874.95
2025-07-28 913.11
2025-07-31 966.87
2025-08-04 985.59
2025-08-08 986.89
2025-08-14 993.43
2025-08-18 1,004.66
2025-08-21 1,005.08