चालू निर्माण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 704.60 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 0 0
Jul, 2024 0 0
Aug, 2024 0 0
Sep, 2024 0 0
Oct, 2024 0 0
Nov, 2024 0 0
Dec, 2024 0 0
Jan, 2025 0 0
Feb, 2025 0 0
Mar, 2025 0 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 37.23 100 37.23
Jul, 2024 103.95 180 103.95
Aug, 2024 103.95 280 103.95
Sep, 2024 235.45 330 235.46
Oct, 2024 247.58 340 247.59
Nov, 2024 349.23 371 349.24
Dec, 2024 449.23 411 408.59
Jan, 2025 624.71 501 453.49
Feb, 2025 759.61 761 461.05
Mar, 2025 759.61 761 541

Instant Demand

Cummulative Demand
Up to Apr-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00