पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर
All amounts in ₹ Lacs
Balance Cost at Start of FY
Works
Sanctioned
Spent
Saving in Works
Resultant Spillover Amount
As Planned in Works
Month | Target | Achivement |
---|---|---|
Apr, 2025 | 20.09 | 6.28 |
May, 2025 | 410.52 | 428.97 |
Jun, 2025 | 1121.28 | 753.42 |
Jul, 2025 | 1697.24 | 1286.24 |
Aug, 2025 | 2040.35 | 1414.46 |
Sep, 2025 | 2327.41 | 1414.46 |
Oct, 2025 | 3054.05 | 1414.46 |
Nov, 2025 | 3423.24 | 1414.46 |
Dec, 2025 | 3830.06 | 1414.46 |
Jan, 2026 | 4317.66 | 1414.46 |
Feb, 2026 | 4830.25 | 1414.46 |
Mar, 2026 | 5063.9 | 1414.46 |
Financial Target/ Achivement
Month |
Annual Demand |
Target By HQ |
Achivement |
---|---|---|---|
Apr, 2025 | 23.79 | 380.34 | 0 |
May, 2025 | 648.81 | 939.99 | 512.68 |
Jun, 2025 | 1346.1 | 1695.55 | 960.79 |
Jul, 2025 | 1907.32 | 1932.55 | 1475.97 |
Aug, 2025 | 2192.87 | 2166.73 | 1579.6 |
Sep, 2025 | 2513.73 | 2681.04 | 1579.6 |
Oct, 2025 | 2967.01 | 3191.45 | 1579.6 |
Nov, 2025 | 3344.35 | 3701.86 | 1579.6 |
Dec, 2025 | 3747.11 | 3983.12 | 1579.6 |
Jan, 2026 | 4219.74 | 4216.42 | 1579.6 |
Feb, 2026 | 4747.1 | 4678.72 | 1579.6 |
Mar, 2026 | 4925.75 | 4678.72 | 1579.6 |
Instant Demand
Cummulative Demand
Up to Aug-2025
62.00 Lacs
History (in Reverse Order)
Allotment
Cummulative Allotment
2666.64 Lacs
History (in Reverse Order)
IFMS Payments