पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 2343.75 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 6 0
Jun, 2024 9 0
Jul, 2024 9 0
Aug, 2024 9 0
Sep, 2024 12 0
Oct, 2024 12 0
Nov, 2024 12 0
Dec, 2024 12 0
Jan, 2025 12 0
Feb, 2025 12 0
Mar, 2025 12.1 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 10 0
May, 2024 5 20 11.24
Jun, 2024 17.62 40.24 106.55
Jul, 2024 97.68 121.8 161.88
Aug, 2024 160.68 129.93 216.45
Sep, 2024 215.99 249.97 273.76
Oct, 2024 264.12 253.58 293.87
Nov, 2024 325.42 285.56 319.41
Dec, 2024 424.88 369.56 415.41
Jan, 2025 583.52 478.63 417.89
Feb, 2025 682.54 663.73 531.48
Mar, 2025 732.54 663.73 732.11

Instant Demand

Cummulative Demand
Up to Apr-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

IFMS Payments