Balance Cost at Start of Fy : 1194.68 Lacs.

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

As Planned in Works

(Cumulative in Rs Lacs.)

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 0 15
Jul, 2024 15 15
Aug, 2024 71 15
Sep, 2024 121 15
Oct, 2024 166 15
Nov, 2024 167.86 15
Dec, 2024 217.86 15
Jan, 2025 272.86 15
Feb, 2025 297.86 15
Mar, 2025 347.86 15

Financial Target/ Achivement

(Cumulative in Rs Lacs.)

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 10.86 0
Jun, 2024 113 21.72 15
Jul, 2024 181 40.74 15
Aug, 2024 199 59.76 15
Sep, 2024 241 135.81 15
Oct, 2024 241 154.83 15
Nov, 2024 271 173.85 15
Dec, 2024 274 192.87 15
Jan, 2025 355.13 211.89 15
Feb, 2025 355.13 230.91 15
Mar, 2025 365.13 287.89 15

Instant Demand History

Cumulative Demand for Next Three Months at a Particular Date

(Cumulative in Rs Lacs.)

01 Apr 2024 0.00
05 May 2024 18.13
06 May 2024 18.13
09 May 2024 18.13
14 May 2024 18.13
15 May 2024 18.13
16 May 2024 359.17
17 May 2024 359.17
18 May 2024 359.17
20 May 2024 389.17
21 May 2024 389.17
24 May 2024 389.17
25 May 2024 389.17
27 May 2024 389.17
28 May 2024 389.17
03 Jun 2024 389.17
30 Jun 2024 389.17

Allotment History

(Cumulative in Rs Lacs.)

01 Apr 2024 0.00
09 May 2024 21.71
30 Jun 2024 21.71

IFMS Payments

(Cumulative in Rs Lacs.)

2024-06-07 15.00