Balance Cost at Start of Fy : 826.48 Lacs.

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

As Planned in Works

(Cumulative in Rs Lacs.)

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 0 0
Jul, 2024 40 0
Aug, 2024 40 0
Sep, 2024 90 0
Oct, 2024 126.05 0
Nov, 2024 151.05 0
Dec, 2024 201.05 0
Jan, 2025 201.05 0
Feb, 2025 251.05 0
Mar, 2025 301.05 0

Financial Target/ Achivement

(Cumulative in Rs Lacs.)

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 199 338.05
Jun, 2024 0 398 342.89
Jul, 2024 40 435.39 342.89
Aug, 2024 40 472.78 342.89
Sep, 2024 90 622.35 342.89
Oct, 2024 126.05 659.74 342.89
Nov, 2024 151.05 697.13 342.89
Dec, 2024 201.05 734.52 342.89
Jan, 2025 201.05 771.91 342.89
Feb, 2025 251.05 809.3 342.89
Mar, 2025 301.05 921.5 342.89

Instant Demand History

Cumulative Demand for Next Three Months at a Particular Date

(Cumulative in Rs Lacs.)

01 Apr 2024 0.00
16 May 2024 714.96
17 May 2024 714.96
18 May 2024 714.96
20 May 2024 914.96
21 May 2024 914.96
24 May 2024 200.01
25 May 2024 200.01
27 May 2024 200.01
28 May 2024 200.01
03 Jun 2024 200.01
30 Jun 2024 200.01

Allotment History

(Cumulative in Rs Lacs.)

01 Apr 2024 0.00
09 May 2024 398.05
30 Jun 2024 398.05

IFMS Payments

(Cumulative in Rs Lacs.)

2024-05-14 338.05
2024-06-20 338.36
2024-06-26 340.74
2024-06-27 343.20