पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 121.83 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2025 0 0
May, 2025 0 0
Jun, 2025 28 0
Jul, 2025 28 0
Aug, 2025 42 0
Sep, 2025 42 0
Oct, 2025 59.5 0
Nov, 2025 59.5 0
Dec, 2025 59.5 0
Jan, 2026 59.5 0
Feb, 2026 70 0
Mar, 2026 70 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 0 0 0
May, 2025 0 0 0
Jun, 2025 28 16.51 0
Jul, 2025 28 20.64 0
Aug, 2025 42 24.77 0
Sep, 2025 42 37.15 0
Oct, 2025 59.5 49.53 0
Nov, 2025 59.5 61.91 0
Dec, 2025 59.5 70.17 0
Jan, 2026 59.5 74.3 0
Feb, 2026 70 82.56 0
Mar, 2026 70 82.56 0

Instant Demand

Cummulative Demand
Up to May-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

IFMS Payments