Balance Cost at Start of Fy : 544.71 Lacs.

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

As Planned in Works

(Cumulative in Rs Lacs.)

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 0 15
Jul, 2024 0 15
Aug, 2024 41 15
Sep, 2024 91 15
Oct, 2024 136 15
Nov, 2024 136 15
Dec, 2024 186 15
Jan, 2025 241 15
Feb, 2025 266 15
Mar, 2025 316 15

Financial Target/ Achivement

(Cumulative in Rs Lacs.)

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 7.5 0
Jun, 2024 110 15 15
Jul, 2024 160 30.44 15
Aug, 2024 160 45.88 15
Sep, 2024 201 107.63 15
Oct, 2024 201 123.07 15
Nov, 2024 231 138.51 15
Dec, 2024 231 153.95 15
Jan, 2025 306 169.39 15
Feb, 2025 306 184.83 15
Mar, 2025 316 231.14 15

Instant Demand History

Cumulative Demand for Next Three Months at a Particular Date

(Cumulative in Rs Lacs.)

01 Apr 2024 0.00
16 May 2024 316.00
30 Jun 2024 316.00

Allotment History

(Cumulative in Rs Lacs.)

01 Apr 2024 0.00
09 May 2024 15.00
30 Jun 2024 15.00

IFMS Payments

(Cumulative in Rs Lacs.)

2024-06-07 15.00