Balance Cost at Start of Fy : 221.66 Lacs.

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

As Planned in Works

(Cumulative in Rs Lacs.)

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 0 0
Jul, 2024 15 0
Aug, 2024 30 0
Sep, 2024 30 0
Oct, 2024 30 0
Nov, 2024 30 0
Dec, 2024 30 0
Jan, 2025 30 0
Feb, 2025 30 0
Mar, 2025 30 0

Financial Target/ Achivement

(Cumulative in Rs Lacs.)

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 15 1.47 0
Aug, 2024 30 2.94 0
Sep, 2024 30 8.8 0
Oct, 2024 30 10.27 0
Nov, 2024 30 11.74 0
Dec, 2024 30 13.21 0
Jan, 2025 30 14.68 0
Feb, 2025 30 16.15 0
Mar, 2025 30 20.52 0

Instant Demand History

Cumulative Demand for Next Three Months at a Particular Date

(Cumulative in Rs Lacs.)

01 Apr 2024 0.00
20 May 2024 30.00
30 Jun 2024 30.00

Allotment History

(Cumulative in Rs Lacs.)

01 Apr 2024 0.00
30 Jun 2024 0.00

IFMS Payments

(Cumulative in Rs Lacs.)