Balance Cost at Start of Fy : 28.17 Lacs.

पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

As Planned in Works

(Cumulative in Rs Lacs.)

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 0 0
Jul, 2024 0 0
Aug, 2024 0 0
Sep, 2024 0 0
Oct, 2024 0 0
Nov, 2024 0 0
Dec, 2024 0 0
Jan, 2025 4 0
Feb, 2025 8.64 0
Mar, 2025 8.64 0

Financial Target/ Achivement

(Cumulative in Rs Lacs.)

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 9.75 0 0
Jul, 2024 9.75 3 0
Aug, 2024 24.9 6 0
Sep, 2024 48.78 18 0
Oct, 2024 48.78 21 0
Nov, 2024 48.78 24 0
Dec, 2024 48.78 27 0
Jan, 2025 56.78 30 0
Feb, 2025 61.42 33 0
Mar, 2025 61.42 42 0

Instant Demand History

Cumulative Demand for Next Three Months at a Particular Date

(Cumulative in Rs Lacs.)

01 Apr 2024 0.00
27 May 2024 61.42
30 Jun 2024 61.42

Allotment History

(Cumulative in Rs Lacs.)

01 Apr 2024 0.00
30 Jun 2024 0.00

IFMS Payments

(Cumulative in Rs Lacs.)