पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 135.36 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2024 0 0
May, 2024 0 0
Jun, 2024 0 0
Jul, 2024 1.5 0
Aug, 2024 3 0.16
Sep, 2024 6 0.16
Oct, 2024 7 0.16
Nov, 2024 7 0.16
Dec, 2024 11.5 0.16
Jan, 2025 13 0.16
Feb, 2025 15 0.16
Mar, 2025 15 0.16

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2024 0 0 0
May, 2024 0 0 0
Jun, 2024 0 0 0
Jul, 2024 1.5 1.5 0
Aug, 2024 3 3 0.16
Sep, 2024 6 6 0.16
Oct, 2024 7 7 0.16
Nov, 2024 7 7 0.16
Dec, 2024 8 8 0.16
Jan, 2025 9 9.9 0.16
Feb, 2025 12 15 0.16
Mar, 2025 15 15 0.16

Instant Demand

Cummulative Demand
Up to Nov-2024

15.00 Lacs

History (in Reverse Order)

05 May 2024 15.00
01 Apr 2024 0.00

Allotment

Cummulative Allotment

6.00 Lacs

History (in Reverse Order)

29 Aug 2024 6.00
01 Apr 2024 0.00

IFMS Payments

2024-08-09 0.16