पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर
All amounts in ₹ Lacs
Balance Cost at Start of FY
Works
Sanctioned
Spent
Saving in Works
Resultant Spillover Amount
As Planned in Works
Month | Target | Achivement |
---|---|---|
Apr, 2025 | 2.69 | 0 |
May, 2025 | 8.44 | 1.97 |
Jun, 2025 | 16.49 | 5.07 |
Jul, 2025 | 21.94 | 5.07 |
Aug, 2025 | 21.94 | 5.07 |
Sep, 2025 | 21.94 | 5.07 |
Oct, 2025 | 21.94 | 5.07 |
Nov, 2025 | 21.94 | 5.07 |
Dec, 2025 | 21.94 | 5.07 |
Jan, 2026 | 21.94 | 5.07 |
Feb, 2026 | 21.94 | 5.07 |
Mar, 2026 | 21.94 | 5.07 |
Financial Target/ Achivement
Month |
Annual Demand |
Target By HQ |
Achivement |
---|---|---|---|
Apr, 2025 | 2.69 | 2.19 | 0 |
May, 2025 | 8.44 | 5.48 | 1.98 |
Jun, 2025 | 16.49 | 8.77 | 5.08 |
Jul, 2025 | 21.94 | 9.87 | 5.08 |
Aug, 2025 | 21.94 | 10.97 | 5.08 |
Sep, 2025 | 21.94 | 13.16 | 5.08 |
Oct, 2025 | 21.94 | 15.35 | 5.08 |
Nov, 2025 | 21.94 | 17.54 | 5.08 |
Dec, 2025 | 21.94 | 18.64 | 5.08 |
Jan, 2026 | 21.94 | 19.74 | 5.08 |
Feb, 2026 | 21.94 | 21.94 | 5.08 |
Mar, 2026 | 21.94 | 21.94 | 5.08 |
Instant Demand
Cummulative Demand
Up to Aug-2025
0 Lacs
History (in Reverse Order)
Allotment
Cummulative Allotment
16.49 Lacs
History (in Reverse Order)
IFMS Payments