पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

Financial Analysis

All amounts in ₹ Lacs

Starting Balance

36.83

Balance Cost at Start of FY

New Works

8

Works

37.09

Sanctioned

0.00

Spent

Savings

14.86

Saving in Works

Final Spillover Calculation

36.83 - 14.86 + 37.09 = 59.06

Resultant Spillover Amount

As Planned in Works

Month Target Achivement
Apr, 2025 2.69 0
May, 2025 8.44 1.97
Jun, 2025 16.49 5.07
Jul, 2025 21.94 5.07
Aug, 2025 21.94 5.07
Sep, 2025 21.94 5.07
Oct, 2025 21.94 5.07
Nov, 2025 21.94 5.07
Dec, 2025 21.94 5.07
Jan, 2026 21.94 5.07
Feb, 2026 21.94 5.07
Mar, 2026 21.94 5.07

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 2.69 2.19 0
May, 2025 8.44 5.48 1.98
Jun, 2025 16.49 8.77 5.08
Jul, 2025 21.94 9.87 5.08
Aug, 2025 21.94 10.97 5.08
Sep, 2025 21.94 13.16 5.08
Oct, 2025 21.94 15.35 5.08
Nov, 2025 21.94 17.54 5.08
Dec, 2025 21.94 18.64 5.08
Jan, 2026 21.94 19.74 5.08
Feb, 2026 21.94 21.94 5.08
Mar, 2026 21.94 21.94 5.08

Instant Demand

Cummulative Demand
Up to Aug-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

16.49 Lacs

History (in Reverse Order)

30 Apr 2025 16.49
01 Apr 2025 0.00

IFMS Payments

2025-05-28 1.98
2025-06-30 5.08