पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 36.83 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2025 2.69 0
May, 2025 8.44 0
Jun, 2025 16.49 0
Jul, 2025 21.94 0
Aug, 2025 21.94 0
Sep, 2025 21.94 0
Oct, 2025 21.94 0
Nov, 2025 21.94 0
Dec, 2025 21.94 0
Jan, 2026 21.94 0
Feb, 2026 21.94 0
Mar, 2026 21.94 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 2.69 2.19 0
May, 2025 8.44 5.48 0
Jun, 2025 16.49 8.77 0
Jul, 2025 21.94 9.87 0
Aug, 2025 21.94 10.97 0
Sep, 2025 21.94 13.16 0
Oct, 2025 21.94 15.35 0
Nov, 2025 21.94 17.54 0
Dec, 2025 21.94 18.64 0
Jan, 2026 21.94 19.74 0
Feb, 2026 21.94 21.94 0
Mar, 2026 21.94 21.94 0

Instant Demand

Cummulative Demand
Up to May-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

16.49 Lacs

History (in Reverse Order)

30 Apr 2025 16.49
01 Apr 2025 0.00

IFMS Payments