Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
10W171 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0सं0 6108/।।। (2)/14-33 (प्रा0आ0)/2014 दि0 19.12.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 17.55 Lacs
Resanction Cost : 17.55 Lacs
Exp. Upto Last Fy : 0.38 Lacs
For CFY 2024-2025
Remaining : 17.17 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.38 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
9 years 4 months ago
19 Dec 2014
Tentative Completion date:
1 month 1 week ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: Alignment Dispute
इस मार्ग में समरेखण विवाद सुलझ नहीं पाने के कारण इस मार्ग को दिनांक 19.01.2024 द्वारा निरस्तीकरण हेतु प्रस्तावित किया गया है। -- as on 26-Apr-2024
Physical Peramenters