Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
15W250 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 7234/।।।(2)/11-117(प्रा्र0आ0)/2011 दिनांक 22-12-2011
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 50.40 Lacs
Resanction Cost : 50.40 Lacs
Exp. Upto Last Fy : 1.76 Lacs
For CFY 2024-2025
Remaining : 48.64 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.76 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
12 years 4 months ago
22 Dec 2011
Tentative Completion date:
1 week 3 days ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 14: AIP Conservator
Bottelneck: no issue
आगणन रू0 349.18 लाख का मुख्य अभियन्ता , पि0क्षे0 के पत्रांक 1417/04 याता0 पि0क्षे0 , /2006 दिनांक 28.12.2016 से सचिव लो0नि0वि0, उत्तराखण्ड शासन को प्रेषित है, पुनः द्वितीय चरण स्टेज प्रथम का आगणन रू0 133.75 लाख मात्र का गठित कर अधीक्षण अभियन्ता , तृतीय वृत्त , लो0नि0वि0, पिथौरागढ के पत्रांक 5033/247 सी0 (याता0-अ0)-03/2023 दिनांक 05.09.2023 से मुख्य अभियन्ता , लो0नि0वि0, अल्मोडा को प्रेषित है। आगणन आपत्तियों में प्राप्त आपत्तियों का निराकरण किया जा रहा है। -- as on 30-Apr-2024
Physical Peramenters