Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 40 | 40 | 0.000 | 40 | 40.000 | 0.000 |
30W616 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5927/।।।(2)/13-31 (प्रा0आ0)/2013 दि0 22-11-13
TS Amount (lakhs) : 11.01 Lacs
Financial Detail
Sanction Cost : 415.63 Lacs
Resanction Cost : 415.63 Lacs
Exp. Upto Last Fy : 7.28 Lacs
For CFY 2024-2025
Remaining : 408.35 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 7.28 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
10 years 5 months ago
22 Nov 2013
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 00: Not Started
Bottelneck: no issue
उक्त मार्ग हेतु जिलाधिकारी उत्तरकाशी के पत्रांक-6691/ग्यारह-विविध 2022-2023 दिनांक- 15 जून 2023 द्वारा क्षतिपूरक वृक्षारोपण हेतु दोगुनी भूमि प्राप्त हो चुकी है। क्षतिपूरक वृक्षारोपण हेतु डिजिटल मैप एवं टोपो सीट मैप पाॅलिगन सेफ में बनाये जाने हेतु कार्यालय अधिशासी अभियन्ता प्रा0ख0लो0नि0वि0 उत्तरकाशी के पत्रांक-2544/वनभूमि दिनांक 06.12.2023 द्वारा मुख्य वन संरक्षक देहरादून को डिमांड ड्राफ्ट प्रेषित किया जा चुका है। डिजिटल मैप प्राप्त होने के उपरान्त वनभूमि प्रस्ताव आॅन-लाईन किया जायेगा। सचिव लो0नि0वि0 एवं प्र0अभि0 के पत्रांक- 147/01(01) व0भू0-3/2023 दिनांक 14-02-24 द्वारा दिये गये निर्देशों के अनुपालन मे इस कार्यालय के पत्रांक- 403/वनभूमि दिनांक 29-02-24 द्वारा कार्य निरस्तीकरण हेतु अधी0 अभि0 छठा वृत्त लो0नि0वि0, उत्तरकाशी को पे्रषित। -- as on 01-Mar-2024