Bridge (ID- 1940 ) Inventory Report

Kotga Bridge On Chainage 8.420 of Chandhar Okhla motor road

Data finalized On 05 Jan 2024

By Er. Mohan Singh

Last Rated On 08 Jun 2024

Rating 2.65%

Categorized As

XXXXX on XX-XX-XXXX

In District : Tehri Under Division : PD New Tehri

General

Bridge Type : Motor Bridge High Level
Structure No : 8/17
Feature Intersected : Chaudhar Okhla Motor Road
Name of Bridge : Kotga Bridge
Nearest Town : Lambgaon
Latitude (Northing) : 30.45315000
Longitude (Easting) : 78.46452400
Construction Year : 2004
Inventory Year : 2022

Geometric

Overall length (in meter) : 12.00
Total No of Span : 1
Maximuam Span (in meter) : 12.00
Span Arragment : 1x12.00
No of Lane : 1.000
Overall Width (m) : 2.000
Carriageway Width (m) : 1.800
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 1.800
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre : 5.400
Road Level at Centre : 1580.000
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 0.0
Design Loading : Footpath Live Load
Load Rating : Footpath Live Load

Super-Structure

Superstructure Type : Truss
Superstructure Material : Steel
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Steel rolled section
Bearing type : other

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided