Bridge (ID- 594 ) Inventory Report

18.00 Mtr Span Kalo Pedestrian Bridge

Data finalized On 20 Aug 2022

By Er. Deepak chandra Upreti

Last Rated On 18 Jun 2024

Rating 11.61%

Categorized As

XXXXX on XX-XX-XXXX

In District : Bageshwar Under Division : CD Kapkot

General

Bridge Type : Pedestrain Bridge
Structure No : 1/1
Feature Intersected : Kalo River
Name of Bridge : 18.00 Mtr Span Kalo Pedestrian Bridge
Nearest Town : Baliyakot
Latitude (Northing) : 30.10606900
Longitude (Easting) : 79.84819600
Construction Year :
Inventory Year : 2020

Geometric

Overall length (in meter) : 18.00
Total No of Span : 1
Maximuam Span (in meter) : 18.00
Span Arragment : 1x18.00
No of Lane : 1.000
Overall Width (m) : 1.800
Carriageway Width (m) : 1.800
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 1.800
Gradient (%age) : 7
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level : 1302.500
OFL Ordinary Flood Level : 1300.500
LWL Low Water Level : 1300.000
Design Velocity (m/Sec) : 5.00
Design Discharge (Cumecs) : 600.00
Soffit Level at Centre : 1304.250
Road Level at Centre : 1305.000
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 0.0
Design Loading : Footpath Live Load
Load Rating : Footpath Live Load

Super-Structure

Superstructure Type : Truss
Superstructure Material : Steel
Wearing Coat Type : Other
Expension Joint Type : Not Provided
Railing/Crash Barrier type : Tubular steel
Bearing type : Not Provided

Sub-Structure

Founding Strata : Bouldery
Abutment Foundation Type : Raft
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : Plum Concrete Block
Bank Protection Right Side of Up-stream : Plum Concreet
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : Plum Concreet
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided