Segment [Id - 9] Detail

NH

111.35 Km

Road ID: 9

National Highway [NH123/507]

Starting from its junction with NH - 72 connecting Vikasnager Kalsi Barkot and terminating at junction with NH- 94 near Barkot bend national highway

राष्ट्रीय मार्ग 72 के जक्ंशन से हरर्बटपुर विकासनगर-कालसी-बड़कोट बैंण्ड़ -राष्ट्रीय मार्ग 94 तक राष्ट्रीय राजमार्ग

Segment ID- 9 :

111.350 Km

Top Surface Condition of A Uniform Segment Section
#/ID Start Chainage End Chainage KM Condition Patches Inventory Date Data status Current Source for Road Surface maintenance
1/11426 1.000 12.000 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12 A: All Ok 0 May 02, 2024 AR
2/11427 12.000 16.000 13, 14, 15, 16 B: Moderate Detoriation 0 May 02, 2024 AR
3/1420 16.000 24.000 17, 18, 19, 20, 21, 22, 23, 24 A: All Ok 0 Nov 20, 2023 AR
4/1421 24.000 32.000 25, 26, 27, 28, 29, 30, 31, 32 D: Renewel Required 0 Nov 20, 2023 AR
5/1422 32.000 41.000 33, 34, 35, 36, 37, 38, 39, 40, 41 C: Heavy Detoriation 0 Nov 20, 2023 AR
6/18887 44.000 60.000 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60 A: All Ok 0 Mar 12, 2026 DLP
7/18895 60.000 65.000 61, 62, 63, 64, 65 A: All Ok 0 Mar 12, 2026 Reconstruction
8/18897 65.000 75.000 66, 67, 68, 69, 70, 71, 72, 73, 74, 75 A: All Ok 0 Mar 12, 2026 Reconstruction
9/18898 75.000 101.000 76, 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91, 92, 93, 94, 95, 96, 97, 98, 99, 100, 101 A: All Ok 0 Mar 12, 2026 Reconstruction
10/18893 101.000 107.000 102, 103, 104, 105, 106, 107 A: All Ok 0 Mar 12, 2026 Reconstruction
11/18892 107.000 111.350 108, 109, 110, 111, 112 A: All Ok 0 Mar 12, 2026 AR

Patch work history from MIS

For Division Segment ID - 5715 Total Achivement of 21.000 Km Reported by Manvendra Singh Negi, Assistant Engineer Civil, NH Div Dehradun on 2023-10-25 08:34:32 against Patch Repair 2023-24 (I)

For Division Segment ID - 5715 Total Achivement of 16.000 Km Reported by Mukesh Saklani, Assistant Engineer Civil, NH Div Dehradun on 2024-10-15 08:26:54 against Patch Repair 2024-25 (Post-Mansoon)

For Division Segment ID - 5715 Total Achivement of 14.000 Km Reported by Mukesh Saklani, Assistant Engineer Civil, NH Div Dehradun on 2025-10-16 14:02:16 against Patch Repair 2025-26 (Post-Mansoon)

For Division Segment ID - 5716 Total Achivement of 12.000 Km Reported by Manoj Rawat, Executive Engineer Civil, NH Div Barkot on 2026-04-29 07:41:07 against Patch Repair 2026-27 (Pre-Mansoon)

For Division Segment ID - 5716 Total Achivement of 12.000 Km Reported by Ashok Chauhan, Assistant Engineer Civil, NH Div Barkot on 2026-10-22 03:45:35 against Patch Repair 2026-27 (Post-Monsoon)


Historic Data :

#/ID Chainage Condition Patches Inventory Date Status
1/11589 60.000 - 111.350 A: All Ok 0 May 09, 2024 Data treated as old on May 24, 2024
2/11588 41.000 - 60.000 A: All Ok 0 May 09, 2024 Data treated as old on May 24, 2024
3/1419 1.000 - 16.000 B: Moderate Detoriation 0 Nov 20, 2023 Data treated as old on May 02, 2024