Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 3.5 | 0 |
10W108 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1440 /।।। -2 /11 - 05 प्रा0 आ0 /2010 दि0 28.3.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 44.10 Lacs
Resanction Cost : 44.10 Lacs
Exp. Upto Last Fy : 2.16 Lacs
For CFY 2024-2025
Remaining : 41.94 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.16 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
13 years 1 month ago
28 Mar 2011
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
प्रभागीय वनाधिकारी अल्मोड़ा द्वारा आन लाईन दिनांक 26.04.2024 को आपत्तियों में प्राप्त । -- as on 26-Apr-2024
Physical Peramenters