Work Profile Report : 10W26

जनपद नैनीताल में ग्राम जैैना से चन्द्रकोट धूरा मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0 547/।।।- (2)/09-44 (प्रा0आ0) /08 दि0 11/2/09

TS Amount (lakhs) : 175 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

175.00

Resanction Cost :

175.00

Tentative Cost :

175.00

Exp. Upto Last Fy :

122.11

For CFY 2025-2026

Remaining :

52.89

Demand :

2.00

Allotment :

40.00

Exp in CFY :

0.95

Total Up to Date Exp :

123.06

Construction Started

Sanction on : 17 years 1 day ago

11 Feb 2009

Physical Progress:

At start of FY 2025-2026 :

45 %

Up to Date :

45 %

Tentative Completion date on : 7 months 2 weeks from now

30 Sep 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
5
4
2.000
2
0.000
0.000

Remark

view all

वन भूमि प्रकरण राज्य सरकार स्तर पर है। 2.00 लम्बाई हेतु निविदा आमंत्रित कर अनुबन्ध गठन की कार्यवाही प्रगति पर है। -- as on 05-Feb-2026

Rating : 76

Forest Case Pending At : 17: AIP Govt of India

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: