Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1 | 0 |
Closed Work 10W338 :
Administrative Approval Detail : 3933/III(2)/21-58(MLA)2017 T.C.-2
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
54.78
Resanction Cost :
54.78
Tentative Cost :
54.78
Exp. Upto Last Fy : 52.05
For CFY 2024-2025
Remaining : 2.73
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 52.05
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
2 years 10 months ago
15 Sep 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंग, इंटर, टाॅप का कार्य पूर्ण, शेष कार्य प्रगति पर। -- as on 05-Dec-2022
Physical Peramenters