Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
Closed Work 10W340 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: chamriya bridge
Administrative Approval Detail : 3933/III(2)/21-58(MLA)2017 T.C.-2
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
77.76
Resanction Cost :
77.76
Tentative Cost :
77.76
Exp. Upto Last Fy : 74.87
For CFY 2024-2025
Remaining : 2.89
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 74.87
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
15 Sep 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 10-Jun-2022