Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 |
11W30 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1950/111-2/06-28/(पा्र0 आ0)/06 दि0 28-09-06
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
142.29
Resanction Cost :
142.29
Tentative Cost :
142.29
Exp. Upto Last Fy : 3.36
For CFY 2024-2025
Remaining : 138.93
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 3.36
none
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
17 years 9 months ago
28 Sep 2006
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: Long Term Forest Approval
इस खण्ड के पत्रांक 53 ए0/24 सी0 दिनांक 24-04-2024 को संयुक्त निरीक्षण तिथि निर्धारित किये जाने हेतु पुनः प्रभागीय वनाधिकारी रामनगर वन प्रभाग रामनगर को लिखा गया है। -- as on 26-Apr-2024
Physical Peramenters