Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 |
11W328 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4520/।।। 2 /15-08 म0मु0घो0/2015 दिनांक 19.06.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
54.60
Resanction Cost :
54.60
Tentative Cost :
54.60
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 54.50
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
9 years 4 weeks ago
19 Jun 2015
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: CA Land
इस कार्यालय के पत्रांक 1040/23 सी0 दिनांक 28.06.2024 द्वारा उपजिलाधिकारी सदर नैनीताल, उपजिलाधिकारी कौश्याकुटोली एवं उपजिलाधिकारी धारी को सिविल सोयम भूमि/वन पंचायत भूमि शीघ्रता से उपलब्ध कराने हेतु पुनः लिखा गया है। -- as on 04-Jul-2024
Physical Peramenters