Work Profile Report [11W570]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता एवं विभागाध्यक्ष, उत्तराखण्ड ला0नि0वि0 देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0 नि0।।। दिनांक 16.05.2023
TS Amount (lakhs) : 469.26 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
469.26
Resanction Cost :
469.26
Tentative Cost :
469.26
Exp. Upto Last Fy :
66.98
For CFY 2024-2025
Remaining :
402.28
Demand :
402.28
Allotment :
213.73
Exp in CFY :
213.73
Total Up to Date Exp :
280.72
Construction Started
Sanction on : 1 year 6 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
85 %
Tentative Completion date on : 4 days 19 hours ago
19 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी०सी० कार्य पूर्ण। दीवारों का कार्य गतिमान। -- as on 25-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand