Work Profile Report [11W577]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E-Letter no 51071 लोक निर्माण अनुभाग- 2 dated 12-09-2023
TS Amount (lakhs) : 42.07 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
42.07
Resanction Cost :
42.07
Tentative Cost :
42.07
Exp. Upto Last Fy :
16.43
For CFY 2024-2025
Remaining :
25.64
Demand :
24.45
Allotment :
10.00
Exp in CFY :
0.16
Total Up to Date Exp :
16.59
Construction Started
Sanction on : 9 months 2 weeks ago
29 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
50 %
Tentative Completion date on : 1 month 1 week from now
31 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0 3 का कार्य पूर्ण। पी0सी0 का कार्य प्रगति में हैं। -- as on 04-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: