Work Profile Report [11W590]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक ई-फाईल संख्या 51071 लोक निर्माण अनुभाग-2 दिनांक 12.10.2023
TS Amount (lakhs) : 37.44 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
37.44
Resanction Cost :
37.44
Tentative Cost :
37.44
Exp. Upto Last Fy :
15.38
For CFY 2024-2025
Remaining :
22.06
Demand :
20.73
Allotment :
20.73
Exp in CFY :
19.59
Total Up to Date Exp :
34.97
In Maintenance After Completion
Sanction on : 1 year 1 month ago
12 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
100 %
Tentative Completion date on : 1 month 3 weeks ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। कार्य अनुरक्षण के अन्तर्गत हैं। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand