Work Profile Report [11W614]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक 212ध्।।। (2)ध्2024-01 (प्रा0आ0)ध्2023 दिनांक 31.01.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
290.20
Resanction Cost :
290.20
Tentative Cost :
290.20
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
290.20
Demand :
290.20
Allotment :
185.00
Exp in CFY :
183.81
Total Up to Date Exp :
183.81
Work completed
Sanction on : 9 months 3 weeks ago
31 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 3 days ago
30 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
6200 मी0 लम्बाई में क्रैश बैरियर का कार्य पूर्ण। -- as on 25-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand