Work Profile Report [11W621]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या उत्तराखण्ड शासन लो0निवि0 के ई-फाईल पत्रावली 56165/61 लोक निर्माण अनुभाग-2 दिनांक 07.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
278.78
Resanction Cost :
278.78
Tentative Cost :
278.78
Exp. Upto Last Fy :
104.72
For CFY 2025-2026
Remaining :
174.06
Demand :
170.00
Allotment :
37.20
Exp in CFY :
37.20
Total Up to Date Exp :
141.91
Construction Started
Sanction on : 1 year 4 months ago
07 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
45 %
Up to Date :
60 %
Tentative Completion date on : 3 months 1 day from now
20 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
डेक स्लैब कास्टिंग का कार्य पूर्ण, अप्रोच का कार्य प्रगति पर। -- as on 01-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand